What to do if a non-standard automation project is delayed? 14-year veteran shares practical solutions: BOM-driven approach + node-level warning system.

2026-08-03 10:01:45

What to do if a non-standard automation project is delayed? 14-year veteran shares practical solutions: BOM-driven approach + node-level warning system.

Just as I was finishing my morning tea, the office door was opened: The production supervisor announced that the main milling machine in the workshop broke down last night, and it will take 3 days to replace the parts; a WeChat message from the procurement department indicated that the import of servo motors is delayed again, requiring an additional 2 weeks; and then a phone call from a customer asking if the equipment scheduled to go live next month could be delivered earlier. Originally, the delivery was delayed, but now it will likely be delayed by at least a month. Not only that, but the potential for breach of contract looms, and will the long-standing customer still place orders with you?

This is likely the most familiar daily routine for most non-standard automation business owners. Many assume that "customization will inevitably lead to delays," but this is not always the case.What to do if a non-standard automation project is delayed??Having worked in this industry for 14 years, I've seen firsthand how frequently delays are treated as the norm.90% of project delays are avoidable.

What to do if a non-standard automation project is delayed? 14-year veteran shares practical solutions: BOM-driven approach + node-level warning system.

1. Don't blame the frontline staff; 90% of delays are caused by information mismatches.

When many bosses encounter delays, their first reaction is that the project manager is not performing, the workers are slacking off, and the procurement department is not following up. After scolding, the same situation repeats itself. Non-standard automation is inherently a custom solution; if there is any mismatch in the process, it will eventually lead to a failure in the assembly stage.

I have analyzed data from over 100 non-standard factories, and the three most common root causes of delays are all related to the process:

Root cause of delaySpecific examplesPercentage
BOM version inconsistencyDesign changes are not synchronized across all stages, leading to incorrect or missing parts purchases.More than 40%
Part status is not transparent.The project manager, through individual inquiries to procurement/workshop/outsourcing, discovered that delays had already passed the adjustment window.30%
No warning about progress.It was discovered on the planned completion date that the parts had not been started, and there was no buffer time to coordinate resources.20%

II. Control Risks from the Source: Utilize BOM to Manage All Stages, Avoiding Errors and Pitfalls.

The starting point for all non-standard projects is the BOM (Bill of Materials). Most project delays originate in the BOM phase. The traditional process is: designer creates the BOM → export to Excel → project manager splits the project → send to procurement/production/outsourcing. Even with one hand-off, errors can occur.

Moges PMS9Leverage BOM as the core driver for the entire process: After designers create multi-level BOMs, the system automatically splits them into standard parts, self-made parts, and outsourced parts, and instantly converts them into purchase orders, manufacturing tasks, and outsourcing orders. It can also automatically compare inventory to calculate procurement gaps. Whenever a designer modifies the BOM, all related task orders automatically pop up change reminders, allowing procurement to adjust orders promptly, thereby avoiding delays caused by incorrect or missing parts from the source.

In Suzhou, a non-standard manufacturing company, each project was previously delayed by an average of 3-7 days due to errors and omissions. After implementing a BOM-driven workflow, the delays have been reduced.The error rate has decreased by 80%, and on-time delivery rate has increased by more than 20%.

III. Process Control: Focusing on nodes is more effective than focusing on individuals. Proactive warnings are more useful than reactive firefighting.

Even if the Bill of Materials (BOM) is accurate, the outsourcing process can still lead to problems: critical components on internally manufactured items are pushed to the end of the queue; external manufacturing plants place your orders after those of others, and only inform you that the items are not yet completed when the delivery date arrives.

A reasonable approach is:Each part is broken down into clearly defined operations, and each operation must be reported as completed, with the system automatically updating the status.. Automatically sends reminders to the responsible person when the planned completion date has passed but the work has not started. For example, if the core component is planned to be completed in 3 days, and the work is not yet in the next process on the 2nd day, the project manager will immediately see it and coordinate the additional order. Automatically reminds you to follow up on external parts 3 days in advance, and find a backup factory if they are not delivered.

The debugging phase is equally crucial: all defects identified during each debugging cycle, along with the corresponding resolutions, are meticulously documented. Defects that remain unresolved will prevent entry into the delivery phase, thereby avoiding delays in the delivery date.

4. If delays are unavoidable, use this logic to minimize losses.

Even if the initial implementation is flawless, unforeseen issues (such as supplier shortages, equipment malfunctions, or customer design changes) are inevitable. If delays are unavoidable, don't panic. Follow these three steps:

  1. Quickly assess the overall system status in just 10 minutes.: Which stage is causing the delay? Can missing parts be replaced with alternative models? When will the parts arrive the fastest? How much will the entire project be delayed? With unified progress management, opening the project list will take only a few minutes to clarify the status, eliminating the need for departments to hold lengthy meetings.

  2. Proactively communicate information with customers, do not withhold information.: Inform the customer one week in advance about a 10-day delay and provide a written confirmation. Most customers will accept this. If you only inform them on the delivery date, they will stop production and wait for the equipment, resulting in significant losses and potential claims for breach of contract or loss of future cooperation.

  3. Internal priority adjustments: Prioritize addressing the most critical gaps. For example, if a purchase order needs to be placed, place it immediately; if a price increase needs to be negotiated, initiate the negotiation. All changes and progress are recorded, eliminating the need to waste time assigning blame. Focus on resolving the issue first.

Concluding Remarks: On-time delivery is the core competitive advantage.

Many individuals working on custom projects often assume that "project delays are a normal industry phenomenon." However, reducing the delay rate from 20% to 5% doesn't necessarily require significant investment in modifications. Simply addressing the issue of information mismatches within the workflow can achieve this.

For customers, selecting non-standard suppliers requires that technical competence is a fundamental requirement.On-time delivery is the true core competitive advantage.Instead of viewing delays as an unavoidable norm, it's better to start by streamlining the BOM (Bill of Materials) process. By addressing and resolving the most easily fixable errors and discrepancies, we can improve on-time delivery rates, which in turn ensures stable order fulfillment.