Debugging Management for Non-Standard Automation Projects: Fixing Delivery Delays Caused by Unrecorded Defects

2026-08-27 10:01:50

Introduction: RMB 20,000 in Penalty for a Single Line Saying Debugging Passed

A few days ago I had tea with the engineering director of a company in Kunshan making 3C non-standard assembly equipment. He complained that he had just paid RMB 20,000 in delay penalty. At the customer's site acceptance, a positioning accuracy deviation was found; looking through the company's debugging records, only "debugging passed" was written, and nobody remembered whether the sensor model had been changed or which parameter had been adjusted during the previous in-house debugging. In the end it took 7 days to fix, and the payment was deducted per contract.

I have heard too many similar complaints. In non-standard automation projects, the debugging stage is the most prone to trouble, yet most companies do not take debugging management for non-standard automation projects seriously, and in the end a lot of the profit they should have earned is eaten away.

Debugging Management for Non-Standard Automation Projects: Fixing Delivery Delays Caused by Unrecorded Defects

1. Three Common Problems in Non-Standard Debugging That Most Factories Have Hit

For non-standard automation equipment, from design to assembly, the last gate is in-house debugging. This step must verify whether all parts, once assembled, can meet the precision, speed, and stability required by the customer. Many projects go smoothly until the end and then fail at the debugging stage. In my 14 years, the three pitfalls I have seen most are:

Problem 1: Records are not systematic and are scattered everywhere

Debugging engineers are used to writing parameters in their own notebooks and casually sending a WeChat message to the team leader after changing parameters. Once the project changes hands or the engineer resigns, the previous debugging records cannot be found at all. With multiple rounds of debugging, nobody can clearly say which round solved which problem and which defects remain.

The most extreme case I have seen: an engineer resigned and took away the debugging records of three machines. The newly assigned engineer spent 12 days re-debugging, turning a profitable project into a loss.

Problem 2: Hard to trace the source when debugging problems occur

When debugging finds that performance does not meet the standard, there is a high probability that an earlier stage went wrong: perhaps the BOM issued the wrong material, perhaps an outsourced part's machining tolerance was exceeded, perhaps the assembly sequence was wrong. To find out, you have to ask purchasing for purchase orders, ask the workshop for machining records, and ask assemblers about the situation. Tracing alone can take half a day and directly delay debugging progress.

Problem 3: Progress is opaque and the project manager learns too late

In many companies debugging progress relies on weekly reports, and the project manager only learns a week later that debugging has already been delayed by 3 days. They could have coordinated engineers to work overtime to catch up, but by the time shipping comes they find it is not finished, directly causing a delivery delay.

Comparison dimensionTraditional debugging managementMoges PMS9 debugging management solution
Debugging recordsScattered in notebooks and WeChat, lost when people changeIndependent files for each debugging round, permanently traceable
Defect trackingVerbal or paper notes, easily missedFull closed loop from defect creation to closure
Problem traceabilityCall across departments, taking half a day or moreOne-click links to purchasing, machining, and assembly records, located in seconds
Progress visibilitySummarized in weekly reports, 3-7 days behindReal-time sync with the project dashboard, automatic delay alerts
Knowledge retentionIn old employees' heads, broken when they leaveArchived into the full equipment history, doubling after-sales efficiency

2. Good Debugging Management Comes Down to Four Details

Many people think debugging management means asking engineers to fill in more forms. That is not right. The core of debugging management is to standardize and retain the information of every debugging round, close the loop on defects, and make progress transparent. No need for big and complete; landing four core details solves 80% of the problems:

1. Manage debugging by round, with closed-loop defect tracking

Non-standard equipment almost never passes debugging in one go: at least 2-3 rounds, at most five or six. Every round must have clear records: who the debugging owner is, start and end times, which parameters were adjusted, what the test results were, and which defects were found. All defects must be marked with a status; unresolved defects cannot be closed, and the project certainly cannot move to the next stage.

Moges PMS9 is built on this logic, supporting independent files for each debugging round and full-process tracking of defects from creation to closure. Unclosed defects automatically appear on the project dashboard, so the project manager can see the progress at any time.

2. Debugging data must be connected with the full process

Debugging is not an isolated stage; when a problem occurs, it must be possible to trace quickly back to the earlier purchasing, machining, and assembly stages. For example, if debugging finds that a guide rail is not positioning accurately, one click shows who the supplier of this guide rail is, what the purchase batch is, who was responsible during assembly, and whether there are assembly exception records. There is no need to call each department one by one, saving at least half a day of traceability time.

3. Debugging status automatically syncs with project milestones

Previously, in many companies the project progress was updated manually by the project manager and easily lagged. Once the debugging status is updated, the overall project progress syncs automatically and is compared automatically with the planned delivery date. If the planned duration is exceeded, the responsible person is automatically reminded to coordinate resources and catch up in advance, without panicking only when the delivery date arrives.

4. Debugging records archived into the full equipment history

In many factories debugging records are lost after debugging ends. If a problem occurs on the customer side after delivery, the after-sales engineer can only retest parameters and spends half a day before finding the problem. Archiving debugging records together with the project into the equipment history means that at any time, by pulling up the equipment number, you can see all parameters and defect records from the original in-house debugging, and after-sales maintenance efficiency more than doubles.

3. Do Not Push Debugging Management Only to Engineers; the Process Needs Preconditions

I have worked with many non-standard factories, and debugging management fails not because engineers cannot do it, but because the company has not made debugging records and defect closure preconditions for delivery. Engineers rush the schedule, often hand over something that is just about acceptable, ship with unresolved defects, and fix it at the customer site, which not only loses reputation but also costs travel expenses and delay penalties.

The right approach is to make it a hard gate in the process: debugging can only start after assembly is complete, and the project can only move to delivery and shipping after all debugging defects are closed. Projects that have not completed the debugging loop cannot proceed to subsequent steps, institutionally preventing engineers from cutting corners and skipping records.

I worked with a factory with annual capacity of 50 non-standard machines. After changing this process, projects delivered with defects dropped from 32% to 7%, on-site debugging time was shortened by an average of 2 days, and in a year more than RMB 200,000 was saved on delay penalties and travel expenses alone.

4. Small Factories Also Need Debugging Management, but Not Big and Complete

There is another common misconception: many owners think their factory is small and has few projects a year, so debugging management is too troublesome and Excel forms are enough. In fact, the biggest problem with forms is that they cannot enforce hard process gates or link data. If an engineer forgets to fill in or fills in incompletely, nobody knows, and when a problem occurs the records still cannot be found.

If you really want to do it, it does not need to be too complex; just get the core points right, without starting with a big and complete overhaul.

Conclusion: Calculate How Much Money Is Wasted at the Debugging Stage

The non-standard automation industry already runs on thin margins; everyone knows whether the money earned on one machine is enough to cover a delay penalty. Many people focus on design cost reduction and machining cost reduction, but few have calculated the internal friction at the debugging stage.

Unrecorded information, slow traceability, and delays—together they eat more profit than you imagine. Take a look at the project settlements of the last three months and calculate how much money was wasted at the debugging stage.