Non-Standard Automation Equipment Debugging Management: Why Do Projects Always Get Stuck at the Debugging Stage?

2026-09-14 10:02:58

In the second half of last year I visited 32 small and medium-sized non-standard automation equipment manufacturers in the Yangtze River Delta.

The numbers that came out were a little painful: more than 80% of the factories had at least one project with a delayed delivery in the past year, and 62% of those delays ultimately traced back to the debugging stage. Either defects kept recurring and could not be fixed out, or the debugging records were incomplete and on-site rectification had no direction, and several departments passed the blame back and forth over debugging problems, burning through the delivery cycle for nothing.

Many owners think debugging is just the wrap-up after assembly and not worth managing with dedicated effort. Yet it is precisely this inconspicuous wrap-up that has held up quite a few projects.

Non-Standard Automation Equipment Debugging Management: Why Do Projects Always Get Stuck at the Debugging Stage?

1. The Three Most Common Pitfalls at the Debugging Stage

In many non-standard shops, debugging management is basically "verbal agreements plus casual notes", all kept in the debugging engineer's head, and when a problem appears people sort it out on site. The pitfalls also concentrate in three places.

The most troublesome is that defects are not closed out, so old problems recur. One factory making lithium-battery inspection equipment had a customer find at the first acceptance that the emergency-stop button responded slowly; the engineer fixed it and said it was done. At the second acceptance the same problem came up again. Looking through the records, nobody could find what had actually been changed last time, whether a part had been replaced or a parameter adjusted, so the whole investigation had to start over, and ten-odd days were gone in one round trip. The root cause is that there is no tracking of a defect from discovery through rectification to closure: whether it was changed at all, and whether it was changed correctly, are both unclear, so delivery depends on luck.

The second is that information is not connected, and people shift blame when problems appear. Debugging finds the positioning accuracy out of tolerance; assembly says it built strictly to the drawing, so the parts must have been machined wrong; machining says the dimensions were inspected, so assembly did not seat it straight; purchasing says the parts were made by the supplier to the required specification. Nobody accepts responsibility, and finally two or three days are spent stripping and re-inspecting. All this internal friction stems from the fact that problems found during debugging cannot be quickly linked to the earlier purchasing, machining, and assembly stages, because each piece of information sits in its own notebook.

The third is that experience does not stay, and newcomers take a long time to get up to speed. Staff turnover in the non-standard industry is considerable, and much debugging experience lives in the veteran engineers' notebooks or in their heads. When a newcomer takes over a project, there is no reference for how similar problems were solved before, so the same pitfalls have to be stepped through again, and a debugging cycle more than 30% longer is very common. Not to mention after-sales once the equipment is delivered: when the customer says the machine moves incorrectly, you cannot even pull up the parameter records from the debugging at the time, so you have to send someone on site to investigate again, and the travel cost cannot even be earned back.

2. Effective Debugging Management Comes Down to Four Key Points

At the mention of "management", many people assume a pile of complicated processes and rules is needed. Debugging management is not that complicated; the core is to record clearly what should be recorded and to track what should be tracked all the way through.

Every debugging round must be recorded separately. Non-standard equipment rarely passes on the first try: at best two or three rounds, at worst five or six. If everything is written on one document, unresolved problems are easily missed. The correct approach is to record the debugging personnel, start and end times, and results of each round separately, list the defects found one by one, and close each one as it is rectified.

Defects must be tracked across the whole chain, and nothing is delivered until it is closed. A problem found in debugging, whether caused by design, machining, or assembly, must be tracked until the responsible party has completed rectification; do not leave a tail of "we will fix it at the customer site". Many factories are used to saving up small problems and fixing them all at the customer site, which hurts the customer experience and, on top of that, costs three to five times as much to rectify on site as in the factory.

Debugging information must be connected to the whole project flow. Debugging is not an isolated step: when a problem is found, you should be able to look up the corresponding part information, machining records, and design drawings directly, without asking other departments for documents. For example, when debugging finds that a cylinder's stroke is insufficient, one click shows the purchased model of that cylinder and the stroke parameter required by the design, without asking design for drawings or purchasing for the order.

Debugging records must go into the equipment's full history and be kept long term. They are important equipment files, useful later for after-sales maintenance and as reference for similar new projects. When building another transfer manipulator of the same type, the clearance to which the guide rail had to be adjusted in the last debugging can be looked up in the history, and newcomers do not have to try and fail all over again.

3. Keep Implementation Simple: Get These Four Things Right First

Quite a few factories go digital and immediately demand extreme precision at every step, and the result is that frontline engineers find it troublesome, resist using it, and eventually it fizzles out. Debugging management is the same: standardize the basic actions first, then optimize gradually.

Spend five minutes at each debugging round to fill in the basic information; do not leave it until the end of the shift, and certainly do not rely on memory. Defects found must carry a status, unresolved defects must be highlighted, and nothing may move to delivery until they are closed. Debugging of different rounds must be recorded separately so that changes in problems can be traced. All debugging records must be filed in one place together with the project's design, machining, and assembly records, so they are easy to consult later.

These actions can also be done in Excel, but that relies on someone watching the process, and things get missed easily. With a dedicated non-standard project management system, the process is bound automatically: when a project reaches the debugging stage a task is generated automatically, and it cannot move to the next step until the record is complete, with no one needed to watch it. Moges PMS9 embeds the debugging process between assembly and delivery, so it follows the project and does not skip steps or miss records.

Conclusion: What You Save Is Real Money

Many non-standard shop owners talk every day about cutting costs and raising efficiency, yet most of the cost is wasted in these inconspicuous steps. One day of debugging delay means rent, labor, and tied-up capital all become costs; getting one small step right means less delay and less rework.

Why not look back at the last machine your factory finished debugging: is every problem recorded?