How to Manage Progress on Non-Standard Automation Projects? A Full-Chain Tracking Guide from Kanban to Process Job Reporting
2026-10-24 13:25:05
The progress of a non-standard automation equipment project is often harder to track than expected. From project initiation to delivery, a customized machine goes through more than a dozen stages: concept design, BOM breakdown, standard-parts purchasing, outsourced machining, in-house machining, assembly, commissioning, and acceptance. If any link sticks, the whole delivery date slips. Many factory owners find that a project is "moving along" everywhere, yet when the delivery node arrives, a single missing screw, an outsourced part still on its way back, or one unreported process is enough to leave them watching the date slip.
Poor progress management costs real money: a delay means retention payments are withheld, urgent orders cannot be inserted, workshop resources sit occupied, and sales keeps pressing for goods. This article takes non-standard automation project progress management as its main thread and explains the common sticking points, the corresponding management actions, and where a system can help.

- Non-standard automation project progress management is node tracking across the full chain of design, purchasing, machining, assembly, and commissioning.
- Based on implementation experience at 200+ customers, the project delivery cycle can be shortened substantially on average.
- About 60% of project delays get stuck on material and outsourcing, and about 30% on process handover and job reporting.
The table below puts "watching progress with people" and "managing progress with a system" side by side. The differences lie mainly in three dimensions: node transparency, data timeliness, and exception warning.
| Comparison dimension | Manual progress watching | System-managed progress |
|---|---|---|
| Node transparency | Asking in meetings, chasing on WeChat | Project kanban shows it in real time |
| Data update frequency | Daily or even weekly | Refreshed instantly on process reporting |
| Exception warning | Discovered only after a delay | Automatic reminder before due |
| Cross-department collaboration | Each department minds its own link | BOM-driven full-chain linkage |
As the table shows, the core value of managing progress with a system is not "one more piece of software" but gathering progress data that used to be scattered across design, purchasing, workshop, assembly, and commissioning onto one kanban, so that everyone sees the same facts. The following sections go through the stages one by one.
1. Where exactly does project progress get stuck
The sticking points of a non-standard project come down to three: material has not arrived, processes have not moved, and nobody is watching the nodes.
Material has not arrived means standard parts and outsourced machined parts have not come back as planned. Once a purchase order is issued, when the supplier ships, when it reaches the plant, and whether it passes inspection on arrival are a chain of actions that, without records, leave the buyer with nothing but phone calls. Outsourced parts are worse: for a part sent out, which queue position it holds at the other factory, how far machining has gone, and when it can be sent back are often unknown.
Processes have not moved means the process flow of in-house machined parts in the workshop is opaque. A part may go through cutting, rough turning, finish turning, milling, grinding, and inspection, each performed by different people on different machines. Without job reporting records, the workshop supervisor can only walk to the machines, and which process is running, which is waiting, and whose hands it is stuck in depend entirely on impression.
Nobody is watching the nodes means project-level milestones are not tracked continuously. When the concept is finalized, when the BOM is fully released, when assembly starts, and when commissioning ends: without clear owners and deadlines, these key nodes easily drag on and on.
2. Making progress transparent with a project kanban
The first step in managing progress is making it visible. The project kanban in Moges PMS9 displays ongoing projects, the current stage of each project, the target delivery date, and the completion status of each link on a single page. The project manager no longer has to ask one by one; opening the kanban shows which projects are on track and which are flagged red.
Project status on the kanban flows through initiation, concept design, machining and manufacturing, assembly and commissioning, and delivered, and each stage has clear entry and exit conditions. For example, entering the machining and manufacturing stage requires the BOM to be fully broken down and purchase and outsourcing orders to be issued; entering assembly and commissioning requires both machined and purchased parts to be in stock.
The benefit of this staged management is that a vague "project in progress" is broken into several measurable nodes. As long as a stage fails to advance, the kanban shows it, and the project manager can pinpoint which link has the problem instead of saying vaguely that "the project is slow".
The target delivery date is another key indicator. Each project sets its delivery date at initiation, and the system works backward from that date to plan completion times for each link. Once the actual completion time of a link exceeds the plan, a warning appears on the kanban, reminding the relevant people to act in time.
3. BOM-driven tracking of material and outsourcing progress
Material progress in a non-standard project is rooted in the BOM. Moges PMS9 takes the equipment BOM as its core, managing standard parts, in-house machined parts, and outsourced parts as three distinct categories, and the progress of every part can be traced to a specific BOM entry.
Standard parts go through the purchasing flow: BOM release generates requisition lines, which are consolidated into purchase orders, and after a purchase order is sent, shipping, receipt, and stocking are tracked. Every purchase order has a status flow: requisitioned, ordered, arrived, stocked. Buyers do not need extra spreadsheets; the status is the progress.
Outsourced parts go through the outsourcing flow: BOM release generates outsourcing lines, an outsourcing order is created and sent to the supplier, and the expected delivery date is recorded on it. After the supplier ships, the warehouse books the outsourced goods in, and the parts become available once they pass inspection. Without a system, this chain leaves outsourcing progress almost a black box.
In-house machined parts go through machining tasks: machined parts in the BOM can be released directly into production to generate machining task orders, and the start, completion, and inspection of every process are recorded in the system through job reporting. Looking at the machining task list, the workshop supervisor knows which parts are being machined, which are waiting, and which are finished.
The progress of all three part categories finally converges on the BOM. Opening the BOM structure tree, the project manager sees the kit completeness of the entire machine: which parts are stocked, which are being purchased, which are outsourced, and which are being machined, all at a glance. This kit completeness rate directly determines whether assembly can start on schedule.
4. Process job reporting and real-time workshop progress
The timeliness of workshop progress depends on whether job reporting is timely. Many factories report through paper work orders or Excel, and data lagging one or two days is normal. Moges PMS9 supports process-level job reporting: after finishing a process, the operator enters actual hours, qualified quantity, and operator in the system, and the system updates that process's status immediately.
Once job reporting data accumulates, several things become possible. First, count the actual hours of each process and compare them with standard hours to find the processes with low efficiency. Second, count each operator's output for piece-rate wage calculation. Third, build a load view of machines and people to help the workshop supervisor balance task allocation.
Process changes are also part of workshop progress management. If the routing needs adjusting or the operator needs changing during machining, the change goes through a process change request and approval flow, and the change history is kept on record, avoiding the information inconsistency that verbal notice brings.
Rework and scrap must be recorded too. When a process goes wrong, whether it is reworked or scrapped, what the cause was, and who was responsible are information that, if not recorded, leaves later quality analysis without a basis. The rework and scrap management module in Moges PMS9 stores this information in a structured way for later traceability.
5. Closing out progress in assembly and commissioning
Once parts are complete, the project enters assembly. Assembly management requires designating an assembly owner, recording start and end times, and tracking assembly status. The commissioning stage is more complex: a non-standard machine may need several rounds of commissioning, and the personnel, results, and defects of each round must be recorded.
Commissioning management in Moges PMS9 supports multiple rounds. Each round can record the commissioning personnel, the result, the defects found, and how those defects were closed. If a defect is not closed, commissioning cannot be considered complete, which avoids the situation where "commissioning was done but the problem was not solved".
Delivery and acceptance is the last link of the project. Delivery management shows delivery status by project, tracks the target delivery date, and records delivery actions. Project status then flows automatically from assembly and commissioning to delivered. After delivery, the equipment history retains the full chain of design documents, machining records, and assembly and commissioning records, which makes after-sales maintenance easier.
6. Suggested pace for small and mid-sized non-standard equipment builders
Progress management does not improve automatically just because a system is installed; the key is the pace of implementation. For non-standard automation equipment builders with 20 to 100 people, a three-step approach is recommended.
Step one: get the project kanban and BOM management into use. These two modules are the skeleton of progress management: the kanban makes progress visible, and the BOM gives every material a home. At this stage not all data needs to be perfect, but three kinds of base data must be accurate: project status, BOM structure, and part type.
Step two: get the reporting flows for purchasing, outsourcing, and machining working. Let purchase orders, outsourcing orders, and machining task orders all be generated from BOM release, and let all status transitions run inside the system. The goal at this stage is to eliminate "black box progress" and make the whereabouts of every part traceable.
Step three: add assembly, commissioning, and cost analysis. Once the data in the earlier links is stable, assembly and commissioning progress naturally keeps up, and cost analysis finally has a reliable data source. Moges has been building manufacturing management software since 2012 and has served 200+ manufacturing enterprises; this three-step method is a path with a relatively high success rate.
The essence of progress management is turning "managing projects by feel" into "managing projects by data". When the status of every link is visible in real time, a delay stops being a sudden accident and becomes something that can be warned about and intervened in ahead of time.