Purchasing Management for a Mold Shop: The Whole Flow from Requisition to Reconciliation
2026-10-25 18:28:12
This article skips purchasing theory and covers one thing: how a purchasing module built for machining and mold shops breaks the chain from requisition to reconciliation into documents, and what each document controls. It follows the actual design of Moges PMS5, step by step.

1. Requisition: Demand Becomes a Document, with Approval
Beyond the three essentials of a requisition, the system adds two safeguards:
- Approval flow: once a requisition is submitted from draft, it goes into pending approval and only becomes approved when the approver signs off, so the demand passes a confirmation before any purchasing money is spent
- Duplicate-purchase prevention: every requisition line records the quantity already converted to a purchase order, and that amount is deducted automatically on conversion. If the same line is converted twice, the second attempt cannot exceed what is left, which closes off buying the same thing twice at the mechanism level
Requisition lines also carry a required date and a purpose, and in the purchasing stage these become the basis for delivery dates and price verification.
2. Purchase Order: Five Statuses Cover a Document's Whole Life
A purchase order is not finished once it is issued; its status keeps changing:
- confirmed: confirmed but not received, so the order is live and waiting for the supplier to deliver
- receiving: partway through a split delivery, with each batch recorded as it arrives
- completed: everything due has arrived
- restocking: after a return, the purchase order reopens and waits for replacement stock. Many systems lack this status, and it addresses the fact that returning goods does not end the order
- cancelled: void
Each line records the received quantity in real time and is linked at line level to the source requisition line, so looking back you can see at a glance how one requisition was split into several purchase orders and how much each converted.
3. Change Order: Amending Is Not a Shout, It Is a Document
When a confirmed purchase order needs changing, the system's approach is to open a purchase change order. The change type is one of five: quantity, price, supplier, delivery date or cancellation. The data before and after the change are each retained, the reason, the person and the time are all recorded, and the change takes effect only after confirmation.
This means the history of any purchase order can answer how many times it was changed, what changed each time, who changed it and why. When a price dispute arises at month-end reconciliation, the change orders hold the answer.
4. Receipts and Returns: Every Step In and Out Is Recorded
Once a receipt is confirmed, stock is automatically put into the designated warehouse, and the lines are linked to the purchase order line by line, so if the same material was ordered on several lines and delivered in several batches, the quantities received do not get mixed up. A mistake can be reversed: a reversal is not a hard delete, and it keeps the person and time of the reversal, so the audit trail stays complete.
Once a return is confirmed, stock is automatically issued, each line is checked against the returnable quantity (you cannot return more than you received), and the purchase order automatically moves into restocking. A return is not an action separate from the purchase order; it grows out of this same chain.
5. Reconciliation: One Statement Settles Five Amounts
A purchasing reconciliation statement is produced by supplier and by period, and five amounts are set out clearly: total reconciled amount, total returns, amount payable, confirmed amount and amount paid. Returns are automatically counted as offsets in the reconciliation, with no manual deduction. The statement goes through a confirmation flow, from sending it to the supplier for confirmation to confirmed, and once confirmed payment is scheduled by the payable due date, with the invoice number attached to the statement.
Requisition, purchase, change, receipt, return and reconciliation: six kinds of documents each govern one stretch, and together they give the whole chain. Whether the last expenditure has a source and when the next batch of material arrives are answered by documents, not memory.
Every document in this chain can be handled for real in the purchasing module of Moges PMS5. The receivables reconciliation on the customer side, the RC statement, mirrors the same logic; see How to Get Through Month-End Reconciliation Without Arguments.
---