Requisition, Purchase, Receive: Three Steps to End "Bought but Unused, Used but Unbought"
2026-10-25 19:07:53
"Bought but unused; used but unbought" — these eight characters describe the two most typical wastes in small-factory purchasing. The root cause: demand never becomes a document. Using Moges PMS5's requisition and receiving modules as reference, this article covers how the first three steps land in a system.

I. Requisition: A Document with an Approval Flow
A requisition in the system isn't a form you fill and forget — it has its own status flow: draft → submitted → approved (or rejected).
- The shop or planner fills the requisition: what (material), how much (quantity), when needed (required date), what for (purpose)
- After submission it awaits approval — only an approver's pass moves it to approved; a rejection sends it back for rework
- Line-level detail management: one material per line, with quantity, required date, and purpose each in its own field
The point of approval isn't ceremony — it's giving "demand that costs money" a second pair of eyes. In a small shop, the approver is the owner himself, one tap on the phone.
II. Converting to Purchase Orders: Duplication Prevention Is a Mechanism, Not Diligence
Once a requisition is approved, it converts into purchase orders. There's an easily missed design here: every requisition line tracks "quantity already converted to PO".
If one line of demand calls for 100 screws and 60 are converted the first time, the system remembers 40 remain; a second conversion attempt of 60 lets only 40 through — the extra 20 can't convert. "Accidental double buys" aren't prevented by a buyer's attentiveness; they're prevented by the mechanism.
Conversion links at line level — one requisition can split into multiple purchase orders (different suppliers, different batches), and every PO line points back to its source requisition line. Later, tracing "which requisition did this batch come from" is a matter of following the link.
III. Consolidation: Handling Scattered Demand in One Place
When several departments requisition the same material in quick succession, the system's answer is consolidation: pool pending requisition lines into one view, merge quantities for the same material, verify specs and quantities, and sequence processing by required date.
Consolidation's value is centralization — one person sees the whole picture, and duplicates and missed lines have nowhere to hide. Changes are absorbed here too: change your mind at the requisition stage and it's one document to edit; after the PO is confirmed, changes must go through an amendment.
IV. Receiving Confirmation: Where the Three Steps Close
When material arrives, open a receiving note linked to the PO, verify it, then confirm receipt — inventory enters the specified warehouse automatically and the PO's received quantities update. Confirmation separates "goods arrived" from "books acknowledged," and mistaken receipts can still be undone (with a trace).
After confirmation, purchased material is visible and issuable in inventory — "bought but unused" becomes visible at a glance: material sitting in stock carries a record of which requisition and which purchase order it came in on.
V. The Value of the Three Steps, Chained
| Waste pattern | Where it breaks | How the three steps plug it | |---|---|---| | Bought but unused | Demand never verified | Requisition approval + mandatory purpose field | | Used but unbought | Each side assumed the other bought it | Consolidated single view | | Duplicate buying | Departments not communicating | Converted-to-PO quantity guard | | Books don't match | Receipts never confirmed | Confirmed receipt auto-warehouses |
Each step is simple on its own; chained together they're a defense line. The system's role is growing every step onto the documents: requisitions get approval, conversions get depletion checks, receipts get confirmation — no reliance on willpower; just follow the documents.
For the full chain beyond these three steps, see the complete purchasing flow and purchase reconciliation; learn about the product at Moges PMS5.
---