What to Do When a Customer Changes an Order at Short Notice: How the Change Review Process Works

2026-10-27 06:08:45

A customer calls and says the delivery date is moving up by ten days, or that they are dropping the job altogether. In a small shop that happens every week. The work already scheduled on the floor has to be rescheduled, material has already been ordered, and outsourced parts are still at someone else's plant. This article is about turning a change from a verbal message into a document, so that changes are traceable and someone is accountable.

What to Do When a Customer Changes an Order at Short Notice: How the Change Review Process Works

1. Changes Come in Two Kinds First

When a customer asks for a change, the first thing is not to nod but to be clear about what is being changed.

One kind is a safe change: only the delivery date moves, or the whole order is cancelled. This does not touch the product structure, the operations or the quantity; its impact is on time and scheduling, and it can still be contained.

The other kind is a dangerous change: a change of quantity, specification, part number or material. Once that happens, work orders must be rescheduled, material recalculated, outsourcing may have been wasted and the quotation may be void. It should not be settled by a planner changing one number on a work order.

In Moges PMS5, customer order changes expose only safe changes: delivery date adjustment, cancellation and forced cancellation. Dangerous changes such as quantity or line item changes are not made at the customer order level; they go through work order changes or a new order. The restriction looks awkward but is a guardrail: narrow the openings where something can be changed casually, and everything left has to leave a trace.

2. The Customer Order Change Document: Three Types

A change goes on its own document, numbered OC{YYMM}{4-digit sequence}, attached under the original customer order. Each of the three types has its own path:

  • Date change (delivery_date): it edits the delivery date field on the order header, a pure field change with no cascade to downstream data. This suits a customer pushing pickup back or bringing it forward a few days.
  • Cancellation (cancel): a soft cancellation that passes the normal guardrail, so only orders still in the pending production state can be cancelled this way. For an order already in production, this document stops you.
  • Forced cancellation (force_cancel): a cancellation that steps over the guardrail. It also cancels the work orders under this order that are still pending or in progress, but it performs no automatic action on downstream links such as outsourcing, shipment and reconciliation, leaving those for manual handling.

3. Original Snapshot, Change Note, Reason: The Three Pieces of the Trail

On a change document, what is really valuable is not what changed but what it was before.

The system stores two JSON snapshots for every change document, original_data for before and new_data for after. There is also a change_detail field holding a human-readable note. The JSON snapshot is for the system to check; change_detail is for the person going through the books three months later. Neither can be dropped.

One more field is mandatory: the reason is required. That the customer asked for a change and why you agreed to it are two different things; the first is an external request, the second an internal judgment. Record only the first and what you see in a retrospective is a pile of customer requests, which amounts to nothing.

A change document has only three statuses: draft, executed and void. A draft can be edited or deleted, and once executed it is locked; the person who executed it and the time are recorded automatically.

4. Why Forced Cancellation Is Its Own Type

Cancellation and forced cancellation are separated because their risk is not on the same scale.

Normal cancellation is open only to orders not yet in production: no material bought, no work dispatched, so cancelling withdraws a plan at almost no cost.

Forced cancellation is cancelling in full knowledge that there is a cost: work has been dispatched, material may already be ordered, outsourced parts may already be at another plant. What the system can do then is stop the work orders that are still pending or in progress, so the floor does not keep burning hours on an order that no longer exists. How to recover the outsourced parts, what to do with material already purchased, whether to negotiate the loss with the customer: the system does none of that for you, and cannot.

Pulling forced cancellation out as its own type serves one real purpose: to leave a conspicuous mark in the system that this order was forcibly cancelled rather than completed normally. Coming across it in the month-end review, you can see at once where the problem was.

5. What the Shop Floor Must Receive After a Change

Executing the change document does not end the matter.

The floor needs to know at least three things: what date this order's delivery has moved to, whether the work already scheduled should continue, and what to do with material already committed. The system can carry the first two, since work orders follow the order and the planner sees the new date. The third is work for people.

This is why the change process needs a review step, instead of whoever takes the call clicking execute. The gate a review has to pass is simple: which work orders, which operations, which batch of material and which outsourcing supplier does this change affect. Once those four questions are answered, execute if it is acceptable, or go back and talk to the customer if it is not, rather than agreeing first and fighting fires on the floor afterwards.

6. The Four Things a Review Should Assess

First, whether material has already been committed. Once material is ordered and parts are started, the cost of cancelling or rescheduling is not in the system but in the warehouse and on the floor.

Second, whether outsourcing is in flight. Outsourced parts are at another plant; whether the outsourcer's date must follow and how the cost is settled has to be discussed separately.

Third, whether the change sets off a chain. Rescheduling one order can push two later orders out of their slots. The system will not work that out for you; the planner has to look.

Fourth, whether this change needs a written account. A request made verbally is easy to deny later. The change note on the document is the evidence you leave for yourself three months on.

Once a change reaches the shop-floor level it goes through a work order change, the CH document; for how work orders themselves are managed, see work order management. To learn about the product, see Moges PMS5.