How to Handle Changes to an In-Progress Work Order? Managing Work Order Changes

2026-10-27 06:08:46

A work order is already in production and the customer wants 200 more pieces; or the customer says one process is no longer needed and should be skipped from the next piece. These two kinds of changes do not take the same path in the system. This article breaks work order changes apart: when to open a change order, why details align to sections, and how far the logs go.

Changes to an In-Progress Work Order? How to Manage Work Order Changes

1. A Work Order Change Is Not Editing the Work Order — It Is Opening a Change Order

The easiest approach is editing the numbers directly on the work order. The shop machines per the new numbers, and nothing seems to go wrong.

The problem comes three months later. The customer says this batch's quantity does not match; you pull up the work order — it shows the changed number, and there is nowhere to check what it originally was. You say it was changed; the customer asks when, who approved it, and why — and you cannot answer.

So the proper practice is opening a change order, numbered CH{YYMM}{4-digit sequence}, hung under this work order. The original work order's numbers stay untouched, and the change order records "what changed from what, why, and who executed it". The work order's currently effective data is the result after the change executes, but every historical modification sits on its own sheet.

This approach has one precondition: work orders cannot be changed out of thin air, nor created out of thin air. Work orders must convert from customer orders, and changes likewise go through documents — this is the basic order of discrete machining; skip it, and the books become untraceable.

2. Four Change Types: Delivery Date, Quantity, Process, Cancellation

Work order changes open four types:

  • delivery_date (change delivery date): the work order's planned completion time adjusts, affecting scheduling order.
  • quantity (change quantity): how many pieces this order produces changes. When quantity changes, material, hours, and costs all follow — this is the type with the widest impact.
  • process (change processes): the section list adjusts — adding one, removing one, or changing a process's planned hours. This type does not touch total quantity, but it changes the process path.
  • cancel (cancellation): this work order will not be made.

Cases beyond the four — changing the product, changing part numbers — are outside work order change scope; those belong to re-opening at the order level or creating new work orders. The change order is not a universal editor — it handles only changes to facts that have already occurred.

3. Details Aligned to Sections: Why Changes Go by Process

A work order's structure in discrete machining: one work order = one product + a sequence of sections + a quantity. Sections are the work order's backbone, so change details also align one-to-one by section.

Each change detail line records: section sequence (seq), section definition, section name, planned hours (planned_hours), section remarks, plus a change-specific set of fields — operation type (add / delete / modify), pre-change planned hours (old_planned_hours), and pre-change remarks (old_remark).

This design solves a concrete problem: the customer says "this heat treatment is no longer needed" — the change order deletes one section; the customer says "this grinding needs more time" — the change is a modify, adjusting planned hours while keeping the original value.

If the change details only say "processes adjusted", the change order is waste paper — the shop does not know which process changed, and the cost difference cannot be computed.

4. Logs in Three States: Create, Submit, Void

Three actions on a change order are logged: create, submit, void. Logs carry the operator, operator ID, operation description, and time.

Why is the log a separate table rather than relying on the change order's status field? Because status only tells you what it is now; the log tells you what happened along the way. A change order may be created, edited twice, and finally voided — the status shows only void, while the log shows the complete saga.

Small factories see plenty of this: the customer says change it in the morning, then says never mind in the afternoon. Voiding the change order is right, but the voiding itself must remain — because the shop may already have acted on the morning's version.

5. Quantity Changes and Process Changes Have Completely Different Impacts

The two change types' processing paths in the system should be viewed separately:

Quantity changes affect material, hours, costs, and delivery. Quantity going from 100 to 150 pieces may leave the material model unchanged (per-piece cost is the same), but machining fees must be recomputed on the quantity basis — depending on the tenant's hour convention: hours per piece or hours per order. Different conventions can make the computed machining fee differ twofold.

Process changes affect the process path and planned hours. One process fewer, and machining fees drop directly; one process more, and both costs and delivery dates need re-estimating. Such changes also often involve outsourcing — a newly added process may not be doable in-house.

So after a change order executes, costs must be recomputed where needed. The system provides a recompute-work-order-cost action per formula: material and machining fees recalculate from the current work order data, section planned hours, and section rates, overwriting the original cost record.

6. When Not to Use a Change Order

Two situations where a change order is not the right tool:

One: it was entered wrong. The planner typed an extra zero into the quantity — that is not a "customer change" but an entry error. Such cases should be voided and re-created or handled as corrections — do not paper over with a change order; the extra change on the books becomes false information at year-end review.

Two: production has not started. The work order was just created without dispatch, and the customer wants changes. Editing the work order directly or withdrawing and recreating is cleaner — a change order is a detour. The change order's value lies in recording "changes that have occurred"; things that have not happened need no change records.

The criterion is simple: has the shop acted on the old data. If yes, trails are mandatory; if not, editing the data itself suffices.

Customer-level changes go through the customer order change order (OC order); what work orders manage, see work order management. For the product, see Moges PMS5.