How to Account for Order Changes? The Costs That Requirement Changes Create
2026-10-27 06:08:50
The customer says one sentence — "we are cancelling this order" — and how much cost does that change erase? Most factories cannot answer. Not because they refuse to calculate, but because work order costs themselves were never calculated clearly — how to count material, how to count labor, and which version to count against after a change: none of the three is defined. This article takes the three apart.

1. Change Costs Are Actually Two Accounts
After a customer change, the factory has two things to compute — many count only one:
The first is the post-change cost: how much this work order will cost under the new convention. This is the number used for downstream scheduling and quoting.
The second is the change-created difference: what the pre-change cost was under the old convention, and how much the two differ. This is the basis for negotiating compensation with the customer — or accepting the loss yourself.
The first is computed; the second is compared. The system helps you compute the first; the second depends on your keeping a number before and after the change.
2. How Work Order Costs Are Built: Material by Volume, Labor by Section Rates
Understand the structure before re-computation is even discussable.
Work order cost sits on one record: material cost (material_cost), machining cost (processing_cost), material loss factor (loss_factor, default 1.0), total cost (total_cost = material cost + machining cost).
Material cost is computed by volume, with the formula:
length(mm) × width(mm) × height(mm) × density(g/cm³) × unit price(RMB/kg) ÷ 1,000,000 × loss factor
Density and unit price come from the material file; dimensions come from the work order. This formula defines its temperament: material cost computes "what this block of material is worth by volume", not "what was actually picked". Cutting leaves saw kerfs and clamp-head losses, so a loss factor compensates — adjusted per the factory's reality, not a fixed value.
Machining cost is computed by section:
Σ (each section's planned hours × that section's rate × quantity coefficient)
Section rates come from section definitions (hourly_rate); planned hours come from the work order's section list (planned_hours, in hours/piece).
3. The Quantity Coefficient: An Easily Overlooked Convention
The "quantity coefficient" in the formula above is easily overlooked yet highly impactful.
It depends on the tenant's hour convention setting (processing_hours_mode):
- Per piece (per_piece): quantity coefficient = work order quantity. The result is the whole work order's machining fee.
- Per order (total): quantity coefficient = 1. The result is the machining fee of "one batch of work", not multiplied by quantity.
The same work order, the same data — the two conventions' machining fees can differ tens of times. This is not a bug; it is two bookkeeping habits: some factories report hours per piece, others treat the whole batch as one hour package.
So when a cost figure looks wrong, the first thing to confirm is not the formula but which convention this tenant uses. Without aligning conventions, every comparison afterward is wrong.
4. Recompute After a Change
Once a work order changes (quantity edited, processes added or removed, planned hours adjusted), the original cost figure is void.
The system provides a formula-based recompute action: read the current work order's dimensions and material, run the material cost formula once; read the current sections' planned hours and rates, run the machining cost formula once; the results overwrite this work order's cost record.
The key is the word "overwrite": recomputing does not add a record — it replaces the current value. So before recomputing, if the old number matters to you (say, negotiating the difference with the customer), record it first — export it, screenshot it, or note it in the change order's remarks.
5. The Part the System Cannot Compute: Comparing the Difference Yourself
This section is what this article most deserves to be remembered for.
The system stores only the current version of work order cost. After the change and recompute, the old value is gone. So the number "how much did the change cost" will not be handed to you — the design has no two coexisting snapshots.
To get the difference, only two paths exist:
1. Record a number before the change (export, screenshot, or note it in remarks), recompute after the change and record again, then subtract. 2. Compute from the change order's original values: the change details hold the original planned hours and original remarks — if material dimensions did not change, an old value can be projected from the old hours × rate.
The second path works only for changes like "process changed, hours changed". Cost changes from quantity or delivery date changes must take the first path.
The essence: what the system provides is a cost calculator, not a change profit-and-loss statement. Computing the loss requires someone pressing the calculator once before and once after the change.
6. Why Outsourcing Fees Are Not Computed Again
One more boundary must be made clear, otherwise computed costs will be inflated.
Work order cost has only two parts: material cost + machining cost. Outsourcing fees are not listed separately.
But this does not mean a cost piece is missing — quite the opposite: it is already inside "labor". Outsourcing a process means sending one section out for machining; that section still hangs on the work order's process chain, and its planned hours and section rate count into machining fees as usual. In other words, outsourced machining's value is already reflected in work order costs through the "labor" part.
So the correct practice is not "adding another entry" but verifying whether that outsourced section's hours and rates are filled correctly. If you stack the outsourcing reconciliation amount onto work order costs again, the same process is counted twice — costs inflate, margins compress, and judgments distort with them.
The outsourcing reconciliation amount's purpose is settlement: sent to whom, how many accepted, how much payable, how much paid — it answers "how much do I pay out", not "how much did this order cost". Two different things — never mixed.
7. Turning Change Costs into Quotation Basis
The final purpose of computing change costs is never again quoting by gut feel.
If a factory computes costs by formula for every work order, a year's accumulation yields a body of data on "what similar jobs actually cost". When a new order arrives, find a few similar work orders by material, dimensions, and processes, and look at their actual costs — far more grounded than quoting by experience.
This is why work order costing deserves serious treatment: it is not just for month-end accounting — it is quotation's raw material. Accurate stored data means accurate quotations; fuzzy data means every quotation is a gamble.