Hour Statistics Never Add Up? The Practice of Automatic Hour Aggregation

2026-10-27 06:13:33

Month-end hour statistics in their most typical form: the team leader holds a sheet of paper recalling — "this order took roughly a few hours". Recalled numbers are inaccurate for costing and unfair for performance. This article covers turning hours into system records, and the fact that hours are actually three different numbers.

Hour Statistics Never Add Up? The Practice of Automatic Hour Aggregation

1. Hours Are Not One Number — They Are Three

"How many hours did this job take" sounds like one number, but in the system it is at least three:

  • Planned hours (planned_hours): estimated at scheduling, hung on that section, in hours/piece. They are the basis for quotation and scheduling.
  • Actual hours (duration_hours): computed at reporting — the time actually used between start and finish.
  • Allocated hours (allocated_hours): when multiple people work one section, that section's hours are split among them by proportion.

Each of the three has its own use, and mixing them causes problems. The most common mistake is one sentence: reporting planned hours as actual hours. The reported figures look nice, but at month-end costing they never match what the shop actually worked.

2. Where Actual Hours Come From: Computed Automatically at Reporting

Actual hours require no manual entry.

Reporting has two time points: start and finish. The worker scans to start at the station, scans to finish when done, and the system computes the duration between the two points onto that reporting record — that is duration_hours.

This algorithm has a precondition: start and finish must be operated at the real time points. Started at 8 a.m., finished at 2 p.m., with lunch and helping elsewhere in between — the system computes six hours. It computes "how long this work occupied the slot", not "how long this person kept grinding".

This is not a flaw — it is a definition. In discrete machining, the time a machine is occupied by a work order is part of the cost, even with stoppages and waits in between. If you need net machining time, that is another approach (equipment networking or segmented manual reporting) — automatic reporting computation does not solve it.

3. How Planned Hours Are Used: Quotation and Scheduling

Planned hours are entered at scheduling, in hours/piece, hung on each section of the working work order.

They serve two purposes: scheduling (how long this process occupies the machine) and cost (machining fees computed as hours × rate). Note the latter — the machining fee in work order costs uses planned hours, not actual hours.

This must be stated plainly, or it gets understood as "the system costs by actual duration". It does not: costs use planned hours, while actual hours serve for afterwards comparison. The reason is simple — at quotation time there are no actual hours, only estimates; for costs to be computable before the quotation, only the estimated version can be used.

Actual hours' value lies in comparison: planned 3 hours, actual 5 hours — where is the gap? Underestimated, or is the process itself problematic? This comparison is what hour statistics truly produce.

4. Allocated Hours: When Several People Work One Section

Discrete machining has a common scenario: one section dispatched to two people together, or three people rotating through the same process. At such times "this section's hours" is a total, and landing it on each person requires allocation.

The system's handling: allocate the section's estimated hours by proportion to the workers who actually participated. The allocation result is recorded on each person's work-section record as allocated_hours.

Operationally there are two entrances:

  • View by section for the whole picture: list all "multi-person sections that are completed" — at a glance, which sections still lack hour allocation.
  • Adjust by work-section record: change one person's allocated hours. There is a constraint here — changing one person's allocation requires validating the others, so "allocated more than the total" never appears.

Allocation is usually done once at month end in bulk; only after allocation can each person's hours be computed.

5. What Each of the Three Numbers Governs

Laying out the three numbers' uses makes them hard to confuse:

NumberWho fills itWhere it is used
Planned hoursEntered at schedulingQuotation, scheduling, machining fee accounting
Actual hoursComputed automatically at reportingPlanned-vs-actual comparison, anomaly investigation
Allocated hoursSplit by proportion at month endPersonal hour statistics, performance

One key point: machining fees use planned hours, not allocated hours. Allocation affects "who did how much", not "how much this process is worth". Keeping the two apart keeps the books clean.

6. Accurate Hour Statistics Require Three Things Done Right

One: report at the real time points. No scan at start, retroactive scans at finish — actual hours go stale. The system cannot enforce this; it depends on shop habits.

Two: planned hours need historical grounding. The first estimate may be gut feel, but after ten runs there is data: what were similar jobs' actual hours — reference it next time. The more estimates are grounded, the more accurate costs and quotations become.

Three: allocate periodically. Without allocation, personal hours stay empty forever; postponing it to year-end means nobody remembers who participated.

None of the three is hard — the difficulty is persistence. When hour statistics are inaccurate, eighty percent of the cause is not a failing system, but one of these three things long neglected.

The next step after hours is costs: see How Work Order Costs Are Computed. The reporting link's practice is in Scan-Code Reporting (B3). For the product, see Moges PMS5.