The Customer Chases Delivery Daily — How to Answer With a Delivery Date That Holds Up

2026-11-02 18:30:39

The customer chases delivery daily — how to answer with a delivery date that holds up

In Kunshan there's a precision-parts shop, twenty-odd people, where production control is a woman in her forties surnamed Zhou. The thing she fears most daily is her phone ringing.

The customer's question is always the same: "When will my batch be ready?" And her action is always the same: open the progress-tracking Excel, find the order's row, and look at the machining-progress cell. What that cell contains boils down to four things — not yet machined; material not arrived; stuck and backloged at some section; sitting at the outsourcing shop, sometimes unattended so long the goods never come back.

Four states, four answers, four troubles: not-yet-machined means estimating when it can be scheduled; material missing means turning to chase purchasing; backlog means judging when it will clear; outsourcing unreturned means phoning to hurry, then waiting again.

Worse, the Excel numbers lag. Machining progress reaches her via team leaders' end-of-day reports; outsourcing status depends on her remembering to ask; receiving waits for the warehouse keeper to have time to key it. She checks in the morning; the customer asks again in the afternoon — nobody can promise that cell is still right. An order may have been inserted, a section jammed, the outsourcing shop delayed again. So every time means re-digging, re-checking, re-estimating — an estimate built on information half a day stale.

Answer two or three times and the answer changes. Change it two or three times and the customer stops believing, and starts asking: "Are you people actually managing this?"

The key here isn't "she answers slowly" — it's two things: Excel is a ledger, not a dashboard — records exist, but a person must dig, assemble, and refresh every time; and the ledger's numbers are outdated anyway — entered by whoever had time, not what's happening on the floor right now.

I. What the Customer Is Really Asking Is Four Things

Break the question apart. When the customer asks "when will it be ready," the real questions are four:

Where is this batch right now; how long will the remaining steps take; is anything stuck in between (material, sections, outsourcing); and how much other work is competing for the machines these days.

The shop knows all four — they're just scattered across several sheets and several people: machining progress in the production controller's progress sheet, outsourcing shipments on another ledger page, material arrival a question for the warehouse keeper, and this week's busyness known only to the owner. When the customer asks, the controller flips between sheets and mentally estimates a number.

Each sheet tells one segment, so the assembled answer naturally shifts. Worse are those four states from the opening — not machined, material missing, section backlog, outsourcing stranded — Excel only shows that they "exist," never which one is worsening: a section jammed three days doesn't turn red by itself.

To answer on the spot, there's only one way: assemble these states together, let one person see everything in one place — and see it as of this moment. This isn't adding features; it's relocating information that already exists.

II. Excel Has Three Built-In Defects for Delivery Answers

Using Excel for delivery answers — the problem isn't the user, it's the tool. Three defects, none avoidable.

Defect one: the numbers are past tense. Progress in the sheet depends entirely on someone keying it. Workers finish; team leaders note it on paper; somebody keys it before end of day. Outsourcing sent and returned waits for the handler to have time. So "completed" on the sheet may mean yesterday; "sent to outsourcing" may mean last week. Answering deliveries with these numbers is answering today's question with yesterday's photo. The busier the shop, the further keying falls behind — precisely when deadlines are tightest, the information in hand is least reliable.

Defect two: one order, three "completions." The controller's sheet marks completion by operation count; the team leader's spoken completion means the batch left the machine; the warehouse ledger's completion means the receipt is checked. Each is reasonable; none matches the others. Asked where things stand, the controller answers "done" per her sheet — then chases and finds it stuck at inspection. She quoted the wrong one of the three "completions."

Defect three: no alarms. No cell turns red by itself. A section backlog three days reads as the same line; outsourcing a week overdue still shows "sent." Deterioration happens in the shop's real logistics, not on the sheet. Unless the controller mentally re-walks every order daily, she can't notice — and daily re-walking time is exactly what she doesn't have.

The compound effect of these three defects is the opening scene: answers must be dug and assembled fresh every time, from stale numbers.

III. Remaining Quantity Has Four Layers — Mixed Together, It's Never Accurate

The four displays the controller sees — not machined, in progress, at outsourcing, done-uninspected — map exactly to four layers of remaining quantity. Most people compute only one layer: how far completed quantity is from planned quantity. The most intuitive layer — and the most wrong. On a 50-piece order with 40 reported complete, it looks like 10 pieces remain, when in fact only the first two operations may be done.

Real remaining quantity has at least four layers, and what the customer cares about is all four combined. Same 50-piece order, four layers spread out: actually 20 pieces' worth of work remains before it's "done."

In progress on the machines: sections started but unfinished — these have progress, duration estimable. Say the third operation has run all morning with 8 pieces still on the machine.

Not yet started: queued in the later sections, untouched.

Already sent to outsourcing: this part isn't in the shop; only the outsourcing shop knows its progress — all you hold is how much went out and how much returned. 15 pieces out, 0 back — all 15 sit inside "incomplete," not one can be under-counted.

Done but not inspected: goods are out but haven't passed inspection — can't count as complete. Small shops that count the 5 awaiting-inspection pieces as finished discover at pickup that dimensions are all out of tolerance — returned goods equal work done for nothing.

Counting only the first layer yields a too-optimistic delivery: looks like 10 pieces remain, while the last three operations haven't moved. Counting only the first two misses the outsourced batch: 15 pieces went out, yet the books still think they're circulating in-house.

Here two easily confused things must be separated: outsourcing's "return" and purchasing's "arrival" are not the same thing. Outsourcing is operation outsourcing — the pieces still belong to this work order; what goes out is a section, and its return means that layer's machining is now secured, reducing remaining quantity. Purchasing buys material — what arrives is only the raw material for this batch; not one piece has been made, so it affects "can we start," not machining progress. Two flows, two ledgers: treat outsourcing returns as material receipt, or arrivals as progress, and your delivery answer points the wrong way.

Only with the four layers laid out separately does a delivery date become computable.

IV. Estimate With Planned Hours, Not Actual Hours

Which hours to use for remaining time is a commonly botched choice. Most shops seen use actual hours, on the grounds that "actual is more real."

Actual reported hours look truer, but they carry two problems: only completed sections have them — unstarted sections have no records at all; and they include pauses, waiting for material, finding people, meals — longer than pure machining time.

Planned hours are the opposite: every operation has one, available whether or not it's run. A five-operation order has all five planned-hours figures before it even starts.

So the correct estimate is: completed sections use actual; unstarted sections use the section's planned hours (per piece) × remaining pieces; in-progress sections use elapsed time plus per-piece remainder × pieces. Note the section's planned hours are recorded per piece — skipping the multiplication undercounts by an order of magnitude.

A concrete example: a 10-piece order, five operations, per-piece planned hours 1.5, 2, 0.5, 3, and 1 hours. Two operations complete, actually taking 42 hours (planned 35); the third is running, with 4 hours elapsed on that machine; the last two haven't started.

Remaining hours: the last two operations (3 + 1) hours per piece × 10 pieces = 40 hours, plus a prorated remainder for the third. Then multiply an equipment-availability factor — if other orders are queued for that machine these days, the factor is 2 or even 3.

This method isn't precise, but it has one enormous virtue: every part of it can be explained. When the customer asks "why five days," you can answer: "The last two operations total 40 hours of machining; the machine has two orders queued, so at double that's 80 hours; running 16 hours a day that's 5 days, plus inspection and warehousing — it ships the morning of day six."

Far better than "three days, probably" — and it's only 10 pieces, so the customer actually listens.

V. Four States, Each With Its Own Estimation

The four displays from the opening each estimate differently as delivery answers. This section covers all four — the controller can use them directly.

First: not yet machined. Remaining hours = sum of unstarted sections' per-piece planned hours × pieces, divided by that equipment's normal daily capacity. One layer to add: the waiting queue — how many orders sit ahead on that machine and how long each needs. The same hour of work is one hour on a free machine, four hours with three orders queued. Excel lacks exactly this queue information — who's ahead of you isn't on any sheet.

Second: material not arrived. This belongs to the purchasing flow, unrelated to the outsourcing flow — material is the raw input for this batch; without it, even starting is impossible. What you're estimating here isn't machining — it's arrival. Ask three things: when does material arrive (purchasing's stated date), must this work wait for full material before starting (or can material-free sections run first), and from receipt to machine, how long? When answering, the material arrival date must be stated as an explicit premise: "Material arrives Wednesday, on the machine Thursday, normally done Friday." Quoting a delivery before material arrives is the most galling kind of delay — not a capability problem, just nobody chasing that arrival call.

Third: stuck and backloged at a section. The test of backlog isn't "finished or not" — it's "how long since something entered without leaving." Several batches queued at a section, each waiting its stretch — one sweep exposes the jammed one. Estimation: total volume still queued ahead at that section ÷ what it can output per day. The truly dangerous case is the "one machine, one person who can do it" section — when it jams, every order before and after moves together.

Fourth: at the outsourcing shop, long unattended, unreturned. The most passive of the four — progress sits in someone else's hands. Estimation relies only on this shop's historical turnaround: how many days similar parts averaged returning, the longest one. First-time vendors: quote the longest experience value. Anything past the normal turnaround: stop answering per the original plan — call to confirm, treat "outsourcing says Thursday" as the only source still worth anything, and prepare a contingency for it not returning.

All four share one underlying requirement: one place where every order's current state is visible at a glance. Scattered across sheets, none of these four methods can function — you'd spend half a day just establishing which order is in which state.

VI. The Outsourcing Segment Is Always the Biggest Unknown

Once outsourced parts leave, the shop loses direct observation of their progress. How you answer that segment's delivery depends on one thing: whether this vendor has historically been on time.

With historical data, look up similar parts' actual turnaround. Same heat treatment: vendor A averaged 4.2 days over the last ten sends, longest 7; vendor B averaged 2.8. These numbers come only from records — memory can't hold them, because impressions of the last three sends overwrite the previous twenty.

Without history, use conservative values. First-time vendors get quoted the longest experience value, not the promised one — promise three days, deliver in seven is far too common in small-shop outsourcing.

And when answering, one sentence must be said: the outsourcing segment is estimated, not controlled. Customers accept "I can't be certain about this segment"; they don't accept "you said three days and it took ten." The former is candor; the latter is breach.

VII. Quote a Range, Not a Day

The most practical advice here, and the most neglected.

"Next Wednesday" has only two outcomes: on time, or busted. And small-shop production — insertions, rework, outsourcing delays, equipment failures — anything pushes the date. So quoting a specific day loses trust over time by mathematical necessity.

A range is a different logic: "earliest Wednesday, normally Friday, at the latest next Tuesday."

Each of the three does its job. The earliest is the ideal case, letting the customer plan his own schedule; the normal is the one you're accountable for delivering; the latest is the floor you must defend — past it, you call and explain proactively.

Customers usually react better to a range than to a single day — they can tell you actually computed it rather than brushing them off. And a range gives them decision room: if "earliest Wednesday" suffices, they stop chasing.

One precondition: the three numbers can't come from thin air. Earliest = remaining hours ÷ maximum capacity; normal = remaining hours ÷ normal capacity; latest = normal plus extra waits for outsourcing or inspection. All three must be explainable.

VIII. One Question, Three Settings, Three Answers

Delivery-chasing happens in three settings, each needing its own answer.

On the phone, on the spot: answer with the range and current position only — never commit to a hard date. Something like: "It's on operation three of five; normally another two and a half days; I'll send you details in ten minutes."

Over WeChat: the best setting, because you can attach images. A screenshot of the work order's progress beats ten sentences. Seeing operations light up green one by one reassures the customer more than any promise.

The customer's boss calls to apply pressure: don't discuss progress — discuss options. Either confirm the date or propose split shipments — ship the completed portion now, easing his pressure. Split shipping is the small shop's most effective card, but only if you can say exactly which portion is done.

All three settings share one rule: position first, time second, options last. Reverse the order and you're defending yourself.

IX. Promised Dates Must Be Auditable

This section covers the link most shops lack.

You promised Friday; Friday passed without delivery — and then? Most shops have no "then." The matter evaporates; next time proceeds as before.

All that's needed is one action: record the promised date and compare it with the actual completion date. One record is worthless; three months of them reveals the pattern: which product types always slip, which operation most often overruns, which outsourcing shop is least reliable.

With that data, delivery answers shift from "by feel" to "by history." If fourteen of the last twenty similar orders slipped, averaging two and a half days, then your quote should carry two and a half extra days — not the ideal case.

This works without a system: one sheet of paper, two columns, promised and actual dates. The hard part is persistence. A system's only advantage is sparing you the manual tallying.

X. A Rush Order Arrives — Which Number Moves First

Insertions are the small shop's normal state. One rush order enters, every running order yields, and every delivery date needs recomputing.

The worst recomputation habit: pushing every order's date back two days uniformly. It looks fair, but it converts orders that could have shipped on time into late ones — the customer hears "everything delayed" and feels worse.

The workable method is tiering: orders near completion don't move (let them finish — every early delivery counts); just-started orders push back (smallest loss); orders with work out at outsourcing follow the return dates (late returns requeue automatically).

The judgment takes minutes — but it requires seeing each order's stage at a glance. Paper routing cards can't do it; they're scattered everywhere. This is why progress must be centralized.

XI. When to Proactively Say "We Can't Make It"

Counterintuitive, but it's the key to keeping customers.

When a date will slip, the earlier you say it, the more it's worth. Five days' warning and the customer can adjust his own production; one day's warning and he can only apologize to his customer; announcing on delivery day means he won't come back.

A simple line triggers the call: if remaining hours ÷ normal capacity produces a date past the promised date, phone them. Don't wait until the final day to look.

And the call must be specific: not "sorry, it'll be a few days late," but "two operations remain on this batch; I compute Friday, two days past the Wednesday you need — I suggest shipping the thirty finished pieces now and completing the rest Friday."

Offer options, not apologies. That's the maximum sincerity a small shop can produce.

XII. The Production Controller's Job Is Really Information Management

Back to Ms. Zhou from the opening. Her role is called production control. Her work looks like "answering calls, flipping sheets, replying on WeChat" — in substance, she is the only person in the shop who assembles the whole picture.

Such roles' typical state: she alone knows every order's progress; she takes one day off and nobody in the shop can answer a delivery question.

That's not her failing — it's the information's storage mode failing. One person carrying all information looks efficient; it is a single point of failure.

Fixing it needs neither a new hire nor her working harder — only turning her Excel into something everyone can read and that refreshes itself. Done, she answers faster, and others can answer in her place.

One observation: production control is the role most easily partially replaced by a system — and most easily liberated by one. Replaced: flipping sheets and matching numbers. Liberated: judgment and communication. The former consumes most of her day; the latter is where her value lives.

XIII. Never Let One Person Be the Only One Who Can Answer

The controller takes three days off and the shop's delivery answers stop dead — the real situation at many small shops.

Fixing it needs no extra hire — it needs "her Excel" becoming readable by others. Three concrete actions:

List every running order with customer, part number, quantity, promised date. Update the list daily, print it, post it in the office.

Mark each order's current section by operation name, not percentage. "At operation four, grinding" beats "60% complete" — the former plugs straight into the hours table for remaining-time math.

Keep a remark saying where it's stuck: at outsourcing, waiting for material, waiting for the customer's drawing confirmation. These three stuck-categories account for the overwhelming majority of delays.

With the three actions done, anyone who can read operations can answer in her place. Maybe not precisely — but never "I don't know."

Cost: one A4 sheet and ten minutes a day. Benefit: the shop no longer has an unreplaceable position.

XIV. In Moges PMS5, What Each Step Retrieves

Everything above was judgment method. On this system, here's concretely what you get.

The work order carries a required date — the day the customer wants it; status splits into pending, in progress, completed, cancelled; quantities carry planned, completed, and defective figures.

Sections hang under the work order in sequence, each with status, dispatch date, planned hours (per piece), and actual start/finish times. Which operation it's on and how many remain — look here.

The four states from the opening each have their landing spot: not yet machined = later sections still pending; stuck at a section = started but long unfinished with everything behind it waiting; material missing = check the purchase order's arrival and receipt records; outsourcing unreturned = the outsourcing order's expected and actual return dates.

Outsourced sections are marked separately, driven by the outsourcing order's start and completion. The outsourcing order records quantity, send date, expected return date, actual return date, and returned quantity — section VI's "how many days this vendor historically averages" needs no separate ledger; actual return dates accumulate into it. The acceptance note records sent quantity and inspected quantity — the difference is what's still outside; whether returns contain defects shows in the quality anomaly sheet's defective quantity.

Report records hold, per work segment: who started, who finished, on which machine, for how long.

Assembled, these numbers form section III's four layers of remaining quantity. But it won't compute a delivery date for you — the system has no automatic scheduling and predicts nothing. That step stays human; the tool only assembles the materials.

Ask this clearly in selection: those wanting "the system auto-generates an estimated completion date" won't be satisfied; those wanting "all judgment inputs assembled on the spot" will find it enough.

XV. A Reply Template You Can Copy Directly

The preceding compressed into one table — fill it in as you go.

What the customer asksWhich number you check firstOne sentence the reply must contain
Where is it nowCompleted sections ÷ total sections on the work orderThe specific operation name — never "almost done"
How much longerRemaining sections' per-piece planned hours × remaining pieces ÷ normal daily capacityA range, not a single date
Is it stuckCheck the four states one by one: waiting material, backlog, outsourcing outsideWhich segment it's stuck at, and for how many days
Can it be earlierThat machine's schedule for the next two daysBeing earlier means other orders push back
Why did it change againThe gap between promised and actual datesThe reason it changed — one thing, not a list

The table's biggest use isn't showing the customer — it's for yourself. If you can't fill it in, what's missing is data, not eloquence.

XVI. Feed Answers Back, and the Next One Improves Itself

Everything above rests on one assumption: that you know whether your estimates are accurate. When it fails, every method is self-comfort. Among shops we've seen, those who can say "our delivery quotes average N days off" can be counted on one hand.

Only one verification exists: when the answer goes out, record that date; when it actually completes, record the real date. Read the two together. Say you promised November 8 and actually finished November 11 — three days off.

Worthless the first time; valuable by the third month; pattern-revealing by six months. At 40 orders a month, half a year is 240 records — enough to show the pattern.

Look at what? Three things.

Direction of deviation. If 8 of 10 orders land later than promised, your estimates are systematically optimistic — add a fixed number of days to everything quoted. If half early and half late, estimates aren't biased — variance is high, and the answer is ranges, not single dates.

Distribution of deviation. Most orders one-to-two days late, occasionally one ten days late — these need completely different handling. The former means capacity is overestimated; the latter means some link failed (outsourcing, material, equipment). Mixing them produces wrong conclusions.

Which operation most often becomes the bottleneck. One shop kept records half a year and found most delays jammed at the same operation — the precision grinding right after outsourcing returns. One machine, one person who can do it. Once found, the fix is concrete: add a person, or schedule that operation earlier.

All three are computable in Excel, provided the two dates were recorded. A system's only benefit is skipping manual tallying — the order already holds the required date, completion provides the actual date; both fields exist, just never compared.

One side benefit: negotiating with customers on this data changes your footing entirely. The customer says "you're always late"; you answer "of the last twenty orders, eighteen on time, two one day late each, cause: outsourcing delay." Far more convincing than "we'll do our best."

XVII. One Thing You Can Do Tomorrow Morning

No system changes, no meetings. List the ten orders currently running and write three numbers for each: total sections, completed sections, and the remaining work (unstarted sections' per-piece planned hours × remaining pieces).

Two discoveries await: some orders — you genuinely don't know which operation they're on; others you thought were nearly done still have three untouched operations behind them. And some you can't even classify into a state — waiting material, backlog, outsourcing — because the sheet never recorded it.

These three discoveries beat any methodology. They show that the reason delivery answers fail isn't phrasing — it's that the sheet in your hand can't even say what "now" is.