Summary of Bottleneck Problems in Mold Enterprise Management and Solutions

2013-08-26 00:00:00

Production processes often go wrong

A plastics products factory mainly produces mobile phone casings. Its main production processes are: mold workshop, molding workshop, coating workshop and assembly workshop, followed by packaging and shipment. In the past, the factory always had problems at the molding process; it often could not start work as planned, which greatly affected the production arrangements of downstream processes such as coating and assembly. Production plans could not be completed on time, the on-time order delivery rate was low, customers complained and even churned, and orders declined. The enterprise carried out several rectifications, but the results were still unsatisfactory.

Cause analysis:

Inadequate planning delays production

To solve this bottleneck in plastic molding production, the teachers of the Xinwei project team went deep into the molding workshop. After careful investigation and analysis, they found that the problems were mainly caused by the following aspects:

Summary of Bottleneck Problems in Mold Enterprise Management and Solutions

1. Inadequate planning: The planning department only issued the Production Plan to the molding workshop, without giving the mold workshop a plan for mold preparation work.

2. After receiving the plan, the molding workshop did not make pre-production preparations. Instead, on the production day it issued a Mold Repair Order according to the product model and notified the mold workshop to prepare the molds needed for production. Only after receiving the Mold Repair Order did the mold workshop look for the molds and inspect and maintain them.

3. The mold workshop and the molding workshop could not cooperate effectively; man-made delays and waiting often occurred, leading to lost time.

4. No one followed up on the mold workshop's work: After the molding workshop notified the mold workshop, no one chased the results of mold inspection and repair. Only when it was time to start production did staff go to the mold workshop to fetch the molds, and only then did they find that the molds were not ready, so they had to stop the machines and wait for the molds, arranging production only when the molds arrived.

5. Non-standard document filling: The Mold Repair Order used by the molding workshop to notify the mold workshop was very complicated to fill in and wasted a lot of time. For convenience and to save time, employees often informed the mold workshop verbally, which frequently led to wrong mold preparation and delayed production.

6. Inadequate mold maintenance: Molds often had problems only when they were received by the molding workshop and set up on machines for debugging and use; the molds had to be removed and sent back to the mold workshop for repair and maintenance, causing long shutdowns while waiting for molds.

7. Chaotic mold storage made molds hard to find. During daily transfer, there were no handover procedures or documents; only when production needed them did people search everywhere for molds, wasting a lot of manpower and material resources and delaying production time.

Measures taken:

Improve the management system

In response to the above out-of-control phenomena, the teachers of the Xinwei project team guided the relevant department managers to take the following improvement measures:

1. Re-sort the production plan issuance process: When the planning department issues the Molding Production Plan to the molding workshop, it must also issue the Mold Requirement Plan to both the mold workshop and the molding workshop. The mold workshop prepares and repairs molds according to the plan, and the molding workshop follows up and draws molds according to the plan. This makes the tasks and responsibilities of each department in the mold preparation process clear and specific.

2. Cancel the Mold Repair Order used for workshop notification and instead have the planning department issue the Mold Requirement Plan to both the molding workshop and the mold workshop, thereby also avoiding the phenomena of molding workshop employees missing or wrongly issuing orders.

3. The Mold Requirement Plan, filled in and reviewed by professionals, clearly indicates the mold product name, notification time, handover completion time, maintenance sequence and so on, and requires the receiving unit to sign for confirmation when it is issued, avoiding buck-passing and errors.

4. Set up a mold management specialist in the molding workshop, responsible for drawing, warehousing and safekeeping molds, conducting quality inspection after mold maintenance is completed, and following up, supervising and inspecting the completion of the mold workshop's plan. Handle mold abnormalities in a timely manner to prevent production delays caused by mold abnormalities.

5. In response to inadequate mold maintenance, formulate a Mold Maintenance Control Card, which clearly stipulates that after mold maintenance, the mold quality must be confirmed by the mold workshop supervisor and the mold management specialist before the mold can be issued to the molding workshop. Planners and auditors check against the control card standards, avoiding the phenomenon of no one confirming mold maintenance status.

6. Improve the mold management system and implement the Mold Inbound and Outbound Warehouse Management Process, stipulating that all molds in the factory are managed uniformly by the mold workshop, and other departments must fill in a Mold Requisition Form and obtain approval from the mold management specialist before drawing molds. After use, they fill in a Mold Inbound Form, which is accepted by the mold management specialist. This effectively avoids the phenomenon of being unable to find molds.

7. At the daily production coordination meeting, check the completion of the Mold Requirement Plan and make timely improvements. The planning department summarizes and compiles statistics on the completion of Mold Requirement Plan tasks every week and gives rewards or punishments according to the results.

Improvement results:

The on-time order delivery rate rose from 45% to 97%

In the second month after the rectification plan was implemented, the on-time start rate of the molding workshop rose from 70% to 92%. By the end of the project three months later, all production indicators of the factory had improved substantially. Among them, the on-time order delivery rate rose from 45% to 97%, semi-finished product piles on the production floors of all workshops decreased, and defective products caused by mold problems in the molding workshop also dropped significantly.

Looking at the above problems and solutions together, using Moges mold production management software can solve all these problems and improve the production performance of mold production enterprises.