How to create an automation project progress table? Small and medium-sized mold factories should stop using Excel haphazardly.
2026-06-04 08:03:38
Last month, I had tea with the owner of an automation mold manufacturing company in Kunshan. He pulled out his phone and showed me three different versions of Excel spreadsheets, explaining that three custom automation mold projects were delayed this month. He said that the total fines from clients alone amounted to nearly 80,000. When I asked him what the problem was, he said that no one could clearly identify the root cause: the production team said they were waiting for external vendors to return the parts, the external vendors said they were waiting for materials, and the procurement team said that the dimensions had been changed without notification. The update times for each spreadsheet were also different, and the project assistant had to spend two to three hours each day just verifying the progress, which was often inaccurate. He asked me how to create an automation project progress table that would avoid these pitfalls. This is a question that many small and medium-sized factory owners have asked us over the years, and today we will share the valuable information we have compiled.

First, understand: The progress of customized automation projects differs significantly from standard mass production.
Many factories start by creating automation project progress reports, often by modifying existing batch production progress sheets or simply creating a blank Excel spreadsheet to fill in. This is a fundamental mistake. Automation projects, whether involving the development of molds for new automation equipment or on-site automation modifications for customers, are typically 90% customized. Each project has unique processes, materials, and delivery requirements, making it impossible to simply switch tools like in batch production. The following three aspects cannot be covered by standard progress sheets:
One is the high degree of collaboration across multiple departments and entities. This includes activities such as creating drawings, purchasing electronic components, precision machining, and outsourced heat treatment, all of which involve at least five to six departments. Furthermore, it requires coordination with external suppliers, which presents its own challenges. Two is the high degree of variability. This includes changes to customer requirements, design modifications, and supplier disruptions, which often lead to adjustments in the project timeline. Manual spreadsheets are simply not sufficient to handle such changes. Three is the low tolerance for errors. Any delay of even one day results in a daily penalty, which can further delay customer production and lead to additional losses. The project schedule must be strictly adhered to.
To create an automated project schedule, you must capture these four core elements.
- Each process node must be assigned a responsible person and a standard time.Many progress tables only list generic tasks like "Machining" and "Assembly." When problems arise, it's difficult to pinpoint the responsible party and determine the required completion time. The correct approach is to break down tasks into the smallest, actionable steps, such as "CNC Rough Machining of Cavity," assigning specific machinists, specifying standard working times, and clearly defining start and end dates. This makes it immediately clear who is responsible for each task.
- Manage external nodes independently, with real-time status synchronization.This is the most common pitfall: many progress reports only include a single "ship out" entry, without recording when the parts were actually shipped, when the supplier promised to return them, or if there were any delays. We have seen too many projects where the external vendor held onto the parts for two weeks after shipment, while the factory's progress report still showed "normal progress," only to discover too late that the deadline had been missed. When creating progress reports, external vendor milestones should be clearly marked, with specific details such as the shipment date, return date, and contact information for the supplier. Update the status accordingly.
- Change information synchronization updates, ensuring everyone sees the same version.It is very common for automation projects to require changes, where a single size modification can impact the timelines of multiple subsequent processes. Many factories' practice is for project assistants to make changes directly in the system without notifying production and procurement, resulting in workshops completing production based on the original drawings, only to discover the error at the last minute, leading to wasted time. A good progress tracking system ensures that everyone sees the latest version, regardless of whether it involves changing timelines or requirements, eliminating discrepancies and misunderstandings.
- Automatically compare planned and actual progress, and automatically issue warnings for delays.No longer requiring project assistants to manually check each table daily to identify which nodes are behind schedule; instead, the system automatically highlights and alerts when a node exceeds its planned time, enabling proactive intervention and preventing delays until the deadline.
From manual Excel to digitalization: Don't make mistakes in the implementation steps.
Many factories claim to implement progress tracking, but immediately try to purchase the most expensive system or incorporate all processes. As a result, the resulting system is too complex, and frontline workers find it too cumbersome and refuse to use it, ultimately rendering it useless. Our practical logic, which is simple and suitable for small factories with annual sales ranging from 10 million to 50 million, addresses the actual needs of these businesses:
First, organize the standard operation library. Even for customized automation projects, 80% of the core operations are common. First, compile these commonly used operations, and then directly call them when starting new projects. This will save at least half the time spent on organizing, eliminating the need to create progress tables from scratch each time.
Step 2: Switch to scanning-based work order submission, replacing manual updates. Frontline workers scan the work order code after completing their tasks, and the progress is automatically updated. This eliminates the need for project assistants to manually visit the workshop every day and fill out the progress in a spreadsheet. We have calculated that, previously, project assistants spent 2-3 hours each day updating progress. Now, it can be completed in just a few minutes, freeing up time for them to focus on more important tasks.
Step 3: Enable multi-end viewing. Sales personnel can report progress to customers, and managers can check production status while traveling. Instead of constantly requesting the latest reports from project assistants, users can directly open their mobile devices to view real-time status. This significantly speeds up information synchronization. The Moges system already includes native mobile app functionality, perfectly matching this need.
Please note that it's important not to immediately focus on comprehensive, all-encompassing solutions. First, prioritize solving the core issue of progress tracking. Implement only the necessary features, and 80% of problems can be solved with 20% of the features. This is the key reason why our project implementation success rate remains above 95%, and why we avoid unnecessary features that can be difficult to use and costly.
Three common misconceptions to avoid
Common Misconception: Progress reports are only viewed by management, and frontline staff do not participate in updates. Many factories have a practice where project assistants update the progress reports, and frontline staff have no involvement. As a result, the actual work processes are already delayed by three days, but the progress reports still show normal progress, rendering them ineffective. It is essential that frontline staff report their progress directly, ensuring the accuracy of the data.
Second Misconception: Each department maintains its own separate spreadsheets, leading to a lack of information sharing. Creating separate progress reports for production, procurement, and external vendors results in version discrepancies and requires coordinating with multiple departments to track progress. This process delays customer inquiries about delivery dates and undermines trust. The core principle of creating a progress report is to ensure seamless information sharing, with everyone using the latest version.
Third Misconception: Focusing solely on the current project without archiving data. After a project is completed, simply archiving the progress table and never looking at it again. In reality, the delayed milestones and actual working hours of each project serve as valuable references for future projects of the same type. Archiving this data will significantly improve the accuracy of future delivery estimates and allow for proactive identification of potential problem areas.
In reality, for small and medium-sized factories, the core of creating an automation project progress table is not just about creating a visually appealing table or implementing complex processes. It's about effectively addressing the three most practical questions: "Where is the project located?", "When will it be completed?", and "Is there a risk of delays?". Many companies are misled into implementing large, comprehensive systems that cost tens of thousands of dollars, but ultimately prove to be unusable. It's much more effective to clearly identify and address the core issues and find tools that are suitable for their scale. Consider reviewing your own factory's progress table. The biggest pain points are often: lack of timely information updates and misalignment between different departments. Once these issues are resolved, most problems will disappear.