Introduction: Production control issues in non-standard projects typically do not occur in the workshop.

Anyone who works with custom automation equipment knows that project delays are rarely caused by a single person's mistake. More often, it's due to a small problem that wasn't addressed early on, which then cascades and affects subsequent stages such as procurement, processing, outsourcing, and assembly.

Many companies initially consider implementingNon-standard automated production management systemThe reason given is 'to track progress'," but in practice, simply viewing Gantt charts has limited value. The production process for non-standard equipment is driven by the project's Bill of Materials (BOM).The BOM (Bill of Materials) was not properly managed, leading to issues with subsequent purchase orders, outbound orders, manufacturing tasks, and assembly shortages, which then required manual monitoring and chasing through group messages.

Non-standard Automation Production Management System: Stop focusing solely on progress charts; the real bottleneck is the Bill of Materials (BOM) and order placement.

1. The core of the system is not "data entry," but rather using the Bill of Materials (BOM) to drive execution.

Many companies fail to implement systems effectively because they treat them as simple spreadsheets. In the manufacturing of non-standard automated equipment, the BOM (Bill of Materials) should be the starting point for production management. The equipment BOM should be able to differentiate between parts and drive different business functions backward.

  • Standard Parts:Convert from BOM to Purchase Requisition Details, then create a Purchase Order, and receive and store the goods after purchase.

  • Outgoing shipments:Convert from BOM to detailed external processing, generate external processing orders, and receive external processing after acceptance, then put it into inventory.

  • Self-manufactured parts:Convert from BOM to processing tasks, execute according to the process steps, and then proceed to the next stage upon completion.

Moges PMS9The design concept focuses on this specific workflow. When a BOM is placed, the system automatically converts the parts into "Purchase Request" or "External Procurement" details, and generates purchasing suggestions based on the quantity shortages. This significantly reduces redundant orders, missed orders, and incorrect orders.

2. Workpieces must be managed by process, otherwise, only "incomplete" will be displayed.

For non-standard equipment, the finished parts are most concerned about having a rough status (only showing "Not started", "In Process", or "Completed"). If the system only records "In Process", the project manager still needs to call around to ask: Is it because the material hasn't been cut, the milling machine hasn't been set up, or the heat treatment hasn't been returned?

A more practical approach is to convert self-manufactured items into manufacturing tasks, and then manage these tasks.Define Work Steps(Name, Hours, Sequence). Real-time reporting by operation, allowing the project manager to see exactly which work order a specific part is stuck on, enabling accurate determination of which parts are ready for assembly preparation.

3. The warehouse is not an isolated entity; receiving and shipping operations must be coordinated with procurement and assembly.

When parts are missing during assembly, the warehouse says they haven't arrived, while purchasing says they have already received them. After further investigation, it is discovered that some are in inspection, and others have not been put into inventory. If there is no connection between purchasing, receiving, external acceptance, processing completion, and inventory, the warehouse data will become "inventory exists, but not on the floor."

For non-standard projects, inventory management is not simply about looking at the total quantity, but rather about ensuring thatReturn to the project, Return to BOM, Return to assembly tasks. A prerequisite for inventory synchronization is clear and accurate BOM (Bill of Materials) ordering in the front-end, and documented execution in the back-end.

4. Assembly and debugging should not only be documented in the WeChat group; clear permissions must be established.

Information during the assembly and debugging phase is most prone to becoming fragmented. A systematic management approach does not require excessive on-site intervention, but the assembly process should at least allow for the creation of tasks, recording of time and status. The debugging phase should support:Multi-stage debuggingRecord defect descriptions and closure status. The project status should automatically update based on actual business operations, rather than relying on a monthly unified status update.

Additionally,Access ControlThis is a very practical consideration. If everyone could freely modify project data, BOMs, and purchase prices, the data would quickly lose its credibility. The system's role-based access control (RBAC) allows for fine-grained permission management, ensuring that administrators and regular users have distinct levels of access, thereby preventing accidental data modification and clarifying responsibility boundaries.

Conclusion: When selecting, don't just ask if there are dashboards; ask if the system can complete the entire project.

To determine if a non-standard automation production management system is suitable, it should be tested with a real-world project: from project initiation, BOM creation, and parts allocation, to procurement, processing, receiving, assembly, debugging, and delivery acceptance, to ensure a closed-loop process.

Before selecting a system, companies should first review a past project that experienced delays: Was the system able to identify the initial point of failure early on? A truly useful system should start with the Bill of Materials (BOM) and connect the entire production chain.