What to do when a non-standard automation project is delayed? Don't blindly pressure people anymore, use this 7-step method to identify the bottleneck.
2026-06-21 10:03:33
Introduction: Project delays are the biggest fear, especially when the reasons are unclear.
Many non-standard automation projects have been delayed, and the most common actions on-site are meetings, follow-ups, and plan revisions. The project manager follows up with mechanical design, mechanical design follows up with procurement, procurement follows up with suppliers, assembly follows up with warehousing, and debugging follows up with assembly. Although everyone appears to be busy, the underlying problems have not been clearly identified: is the BOM incomplete, or are standard parts missing? Is the outsourced order not returned, or is the self-processing process stuck? Has the assembly not started, or have the debugging defects not been closed?
What non-standard projects fear most is not a delay of a few days, but rather...It's unclear where this information was obtained.. If project managers can only rely on WeChat groups, Excel spreadsheets, and phone records to gather information, they are often left to make judgments based solely on experience, which ultimately leads to situations where "the loudest voice prevails." This is not simply an issue of execution; it stems from the fact that the project process has not been broken down into trackable milestones.
I. Avoiding the Two Major Pitfalls in Project Delay Management
I. Avoiding the Two Major Pitfalls in Project Delay Management
Before developing a strategy, we need to first address two common management misconceptions:
Misconception 1: Attributing delays simply to a lack of "execution capabilities."More non-standard projects, mixed materials, and longer processing paths. If the daily progress reports only state "procurement is in progress" and "processing is in progress," this information provides no help in determining delays. Project managers need precise information such as "Which BOMs have not been ordered," "What is the shortage of standard parts," and "Which processing step is causing a bottleneck."
Pitfall 2: Focusing solely on the overall delivery date, without paying attention to the status of each stage.Delays often begin to manifest in the earlier stages. For example, if the Bill of Materials (BOM) is not fully completed at the beginning of the month, it can lead to a delay in placing orders in the middle of the month, and then shortages are discovered during assembly at the end of the month. A more reliable approach is to clearly define the project's status and workflow (e.g., Initiation - Design - Manufacturing - Assembly - Testing - Delivery), and to proactively intervene when the status does not progress according to the planned timeline.
II. Differences between traditional management and systematic node tracking.
To better understand the importance of process decomposition, we can compare the differences in management between traditional methods and the introduction of professional systems (such as Moges PMS9):
| Management Dimensions | Traditional methods (WeChat groups/Excel/verbal reports) | Systematic Management (Moges PMS9) |
|---|---|---|
| BOM and Order Placement | Manual screening leads to missed opportunities and errors, resulting in delayed procurement initiation. | Hierarchical BOM structure, one-click generation of purchase requests and vendor invoices. |
| Processing Progress | Only knowing "during processing" but not knowing which specific operation is causing the bottleneck. | Process-level tracking, with clear visibility of status from "Pending" to "Completed" |
| Assembly and Debugging | Communication relies heavily on verbal communication, and there is no closed-loop record for debugging defects. | Task assignment to personnel, complete record of defect description and closure status throughout the entire process. |
| Deferred inspection | Wasting time in unproductive meetings, relying on guesswork, and lacking data-driven analysis. | Trace back from the main project workflow, 7 steps for precise pinpointing of bottlenecks. |
3. The starting point for deferred troubleshooting: Start with the BOM, not the workshop.
Delays in the implementation of non-standard automation equipment often stem from issues within the Bill of Materials (BOM). When the BOM is not clearly defined, procurement, outsourcing, and in-house manufacturing processes cannot be accurately initiated. This is particularly problematic with multi-level equipment structures where standard parts and manufactured parts are mixed together, making manual sorting highly prone to errors.
Within Moges PMS9, project Bills of Materials (BOMs) are structured hierarchically for each project, distinguishing between standard parts, parts manufactured in-house, and parts outsourced. Once the BOM details are organized, parts are converted into purchase requests or outsourcing specifications through the ordering process. The system then provides purchasing recommendations based on the number of missing parts. When investigating delays, the following three points are recommended:
Is the Bill of Materials (BOM) complete?Are there any parts that are still only listed in the design table but have not been added to Project BOM?
Order completion status:Does the standard component trigger a purchase action, and does the outgoing item enter the outgoing processing workflow?
Is the gap clearly defined?Instead of asking "Do we have the materials?", the focus should be on determining the exact quantity needed and identifying which materials are critical for assembly.
4. Machining, Assembly, and Debugging: Transforming ambiguity into clarity.
1. If a work order is delayed, it's important to identify the specific operation that is causing the delay.Semi-manufactured items are most prone to the ambiguous state of "the workshop says it's in progress, but no one knows which step is stuck." The system defines the process name, processing time, and sequence for semi-manufactured items, and creates processing tasks after production. This allows for identifying whether the task has not been started or if a specific process is delayed. Similarly, for items outsourced, it is necessary to track the acceptance and receiving actions, to avoid the situation of "the item is back but not in stock, and assembly cannot obtain the materials."
2. Assembly delays often represent a concentrated manifestation of earlier problems:Material shortages, incorrect hole positions, and unsynchronized design changes all tend to occur simultaneously in the assembly area. Assembly management should at least achieve the following: clearly defined tasks: which project, who is responsible, start and end times, and on-site anomaly notes. This allows for distinguishing whether scheduling issues or material issues are the cause of the inability to continue operations.
3. Debugging delays must be documented with a closed-loop process:Non-standard equipment often requires multiple rounds of debugging, and detailed records must be kept for each round, including the personnel involved, the results obtained, the defect descriptions, and the resolution status. Otherwise, the project manager will only see the equipment as "still being debugged," making it impossible to accurately explain the actual reasons to the client.
V. Practical Guide: A 7-Step Troubleshooting Method for Delays in Non-Standard Projects
If delays occur, it is not recommended to immediately hold a meeting to assign blame. A more effective approach is to trace back from the main project workflow, and clearly present the actual status of each stage:
Project Overview:Is the target delivery date clearly defined? What is the current status, and which stage is it currently in? Is the responsible person clearly identified?
Check the BOM:Are the multi-level BOMs complete? Are the classifications of standard parts, externally sourced parts, and self-manufactured parts correct?
View Orders:Please verify that the detailed purchase information and external processing details have been created, and that there are no outstanding parts that have not been ordered.
Focus on Manufacturing:Is the self-manufactured task ready for production? Are the sequence of operations and completion status clearly defined?
Warehouse View:Are the actions of receiving, receiving, and verifying completed processing aligned?
Focus on Assembly:Are the assembly tasks started, with complete information for the responsible person, start and end times, and on-site notes?
Observe the debugging process:Can the debugging steps, defect descriptions, and closure status be accurately linked to specific issues?
By analyzing the production line, the reasons for delays are usually clear. Identifying the next steps (e.g., placing new orders, expediting external deliveries, adjusting processing sequences, and consolidating debugging defects) can prevent the situation where "everyone is busy, but no one knows which tasks are critical."
Conclusion: The essence of management is to expose problems early.
Delays in non-standard automation projects are not uncommon. What truly creates a management gap is:Time of issue discoverySome companies only realize they are too late when they are chasing up orders with customers, while others identify risks before the BOM is submitted or processing has started.
Project managers don't need to constantly chase everyone to get updates; instead, they should enable sales to handle order placement, project initiation, BOM design, outsourcing, in-house manufacturing, assembly and testing, and delivery acceptance, creating a continuous record at each stage. If the company currently relies primarily on Excel and group messages for project management, we recommend starting with a typical, frequently delayed project to run the entire process end-to-end. Once the process is clearly defined, bottlenecks will naturally become apparent.