Total lead time for non-standard factory machine processing? How does the machine processing production planning and management system solve practical problems?
2026-06-24 10:03:49
Introduction: Milling operations facing delays are a "high-risk area" for non-standard manufacturing plants, leading to potential breach of contract penalties.
I have 14 years of experience in the non-standard automation industry, serving over 200 manufacturing companies. My analysis shows that over 70% of project delays are caused by planning chaos in the self-manufacturing phase.Machining operations contributed over 60% of the total delay days..
Last month, I had a conversation with the owner of a Kunshan-based company specializing in new energy testing equipment. He stated that he had already incurred two breach of contract penalties this year, totaling nearly 150,000 yuan. One project, valued at 2.8 million yuan, was delayed due to an incorrect sequence of operations for the core machine frame. The urgent task was pushed aside in the workshop, resulting in a 14-day delay and a penalty of 5 points. The problem lies in... It is not due to a lack of raw materials or unskilled workers, but rather...Production planning relies entirely on manual scheduling and handwritten work orders.The process of identifying and resolving issues on the shop floor relies heavily on direct communication and investigation, which inevitably leads to confusion and errors."

4 Common Mistakes in Non-Standard Factory Machine Processing Planning
Many owners, upon seeing low machining efficiency, immediately consider adding equipment or replacing their existing 5-axis machining centers. However, for most small and medium-sized non-standard manufacturers, the utilization rate of their existing machining equipment rarely reaches 50%. The core issue lies in the lack of a well-defined production process. Common pitfalls include:
| Common Management Mistakes | The severe consequences and hidden costs resulting from |
|---|---|
| 1. Manual task splitting leads to errors and omissions. | Once the BOM is generated, the scheduler manually sorts semi-finished parts, standard parts, and externally sourced parts. This process is prone to missing critical components, leading to the discovery that parts are not manufactured until assembly, which directly delays the entire factory's delivery. |
| 2. Lack of transparency regarding process progress | The scheduler spends approximately half of their day in the workshop, checking on progress. However, the information obtained is not always accurate. Workers say "it's almost done," but in reality, the process has been stalled for three days, and by the time it's discovered, it's too late to salvage. |
| 3. No records of returned or scrapped items. | The same part is repeatedly produced incorrectly, resulting in wasted materials and labor, which leads to a confusing accounting situation. The actual losses are not discovered until the project is settled, and it is unclear which specific stage caused the loss. |
| 4. Inaccurate work hour data | End-of-month reporting issues: Actual working hours and planned hours do not match, leading to inaccurate piece-rate calculations. Project costs are entirely based on estimates, and the owner has no way of knowing whether in-house processing or outsourcing is more cost-effective. |
These issues are fundamentally not human-related; they stem from the lack of a management process specifically designed for non-standard, "one-off, small-batch" production. Relying on human management to handle these situations is simply not effective.
Core Logic: BOM-driven planning for the entire machining process.
Many general-purpose production management systems are not well-suited for the specific requirements of non-standard automation. Non-standard projects involve unique parts, making it impossible to rely on standardized, mass production. A truly effective system needs to...Machine Manufacturing Production Planning and Management System, the core isDriven by BOM for end-to-end processes..
WithMoges PMS9For example, after BOM order splitting, the system automatically generates a unique processing task number for each self-manufactured item, automatically matching the standard processes pre-defined by the company, directly assigning the task to the account of the operator responsible for the corresponding process, without requiring manual order creation by dispatchers. Dispatchers can view the status of all tasks (pending, in progress, completed) on the background dashboard, and can directly coordinate with the operator if a process is blocked, eliminating the need to spend time in the workshop every day.
Furthermore, custom machine processing often requires modifications to the manufacturing process due to design changes. An excellent system supports the application and approval of process changes, and all changes are recorded, allowing for the direct retrieval of historical records for the same part during subsequent production, thereby avoiding repeating mistakes.
Process-based management and inventory synchronization: Eliminating hidden waste.
Many manufacturing costs are hidden and often go unnoticed. For example, finished parts are left in a corner of the workshop and forgotten, leading to difficulties in assembly and requiring re-manufacturing, resulting in double the cost. The key to solving this problem is to implement practical solutions.Work Order SubmissionAndInventory Synchronization.
Standard Operation Library and Barcode-Based Work Order:Companies can organize commonly used processes into a standard library and pre-define the time required for each process. Once a process is completed, workers can directly report the work in the system, entering the actual time spent, the number ofQualified products, and the reason for any waste. The system automatically calculates the piece rate, eliminating the need for manual calculations at the end of the month. It also accumulates actual working time data, improving the accuracy of future production scheduling.
Automatic Inventory Synchronization:Once processing is complete and quality inspection passes, the system automatically triggers an inventory notification. After the warehouse receives the goods, the data is synchronized to the assembly department, and information can be retrieved by scanning the number when taking items, eliminating the absurd situation of "finished processing but cannot find." This ensures that the assembly progress is not interrupted.
Commonly overlooked but critical details: Cost accounting and access control
Many factories' systems only focus on production scheduling, without considering cost and permissions, which directly determines whether the system can be used long-term.
Multi-dimensional cost aggregation:Each self-manufactured item's materials, labor hours, and waste automatically accrue to the corresponding project. The owner can see at any time how much money has been spent on a particular project in the self-manufactured stage, whether it is profitable or not. If the self-manufactured cost of a certain part is higher than outsourcing, the strategy can be adjusted in a timely manner to avoid losses.
Fine-grained permission control based on RBAC:Excessive permissions can lead to the leakage of confidential information, while overly granular permissions can be difficult to configure. Moges PMS9 offers hundreds of configurable permissions (187 for administrators and 22 for regular users). Regular operators are only granted reporting permissions for the specific tasks they need to perform, with clear distinctions between what they can see and what they can modify, ensuring both security and control.
Conclusion: First address the fundamental issues, resulting in a direct reduction of 10% in wasted costs.
Many non-standard manufacturing plants aim for a complete and comprehensive digitalization solution all at once. However, for the machining process, it is more effective to firstAvoid work loss, avoid delays, and accurately calculate costs."By addressing these fundamental issues, you can directly reduce at least 10% of wasted costs and avoid significant financial penalties.
If more than half of your projects are delayed due to machining, it might be beneficial to first review and optimize your work assignment and tracking processes, specifically focusing on identifying potential issues in the foundational stages. Choose the right tools to recover lost profits and reputation.