Calculating compensation for delayed non-standard automation projects: How to calculate the compensation.
2026-07-03 08:02:06
A real and tragic case: Delayed by 10 days, all 150,000 profits are lost.
Two weeks ago, I had tea with the owner of a mold factory in Kunshan that specializes in custom automation solutions. He took out a cigarette, lit it, and sighed, saying that the automation line locating fixture project he completed for a specific new energy customer last month was delayed by 10 days, and the customer directly deducted 120,000 RMB as compensation.
Initially, the entire project was only expected to generate a profit of 150,000, but after accounting for all expenses, we essentially lost money, and we also incurred significant material costs. I reviewed the contract thoroughly, but I still couldn't understand the exact calculation. I'm not sure whether we actually lost money or if we simply made a poor decision.
In reality, for small and medium-sized manufacturers, especially mold factories, that transition to automated solutions, approximately 8 out of 10 encounter delays and compensation disputes. Many people ultimately fail to understand the situation.How to calculate compensation for delayed automation projectsEither you will suffer a loss, or you will damage your relationship with the customer and lose long-term cooperation.

Establish a clear baseline: Not all extensions will be accepted, and the other party will be responsible for the consequences.
Many people's first reaction when encountering a problem is to think about the cost. However, this is not always the correct approach.The fundamental prerequisite for all compensation calculations is to first clearly define responsibility. It is not sufficient to simply delay the completion of the work by the other party to trigger compensation.This is the biggest pitfall that most small and medium-sized factories fall into: failing to clearly define responsibilities in the contract. This leaves the customer with the ability to blame you for any issues that arise.
In the projects I've worked on, at least 60% of the delays are not due to the client's side. The most common causes are:Disclaimer by the Client:
The client made changes to the design and technical parameters midway through, requiring the other party to wait for confirmation. This time should be deducted from the total delay period.
Due to delays in the client's advance payment and milestone payments, the other party has been unable to procure raw materials, resulting in a delay in production. This delay will not be considered as a delay caused by the other party.
The client's site lacks the necessary conditions for delivery and commissioning (such as unrenovated facilities and unpowered electrical systems), which prevents the other party from entering the site.
Force majeure (such as pandemics, logistics disruptions, and delays in the import of core components) will result in a default extension of the production schedule, as per industry standards.
Simply put, if the client's own actions cause delays, you will not be responsible for any financial losses. Many bosses are simply unwilling to confront clients or fail to document the process, ultimately leading them to concede defeat.
Standard calculation logic: The algorithms used in the row-level rules are transparent.
Once the responsibility is determined and it is confirmed that the delay was caused by the other party, the next step is to calculate the compensation. Currently, the standard algorithm used in the domestic non-standard automation industry generally involves two steps:
Step 1: Calculate the actual number of days of delay.
It is not sufficient to simply subtract the contractually agreed delivery date from the actual delivery date. Instead, all delays caused by the client's responsibilities must be deducted first. For example, if the contract specifies a delivery date of 60 days, but the actual delivery date is 70 days, and 8 days are spent waiting for the client to revise the design and confirm it, then the actual delay is only 2 days, not 10 days.
Step 2: Calculate the compensation amount.
Two commonly used calculation methods are employed in the industry:
| Calculation method | Specific rules and operating procedures | Suitable Applications |
|---|---|---|
| Fixed daily payout | The contract should clearly state the amount of compensation for each day of delay (e.g., 1000 yuan/day). | Small projects, simple calculations, but be mindful of the overall amount limit. |
| Proportional compensation (most common) | Calculate based on the daily percentage of the unfulfilled amount.The average daily loss ratio falls between 0.1% and 0.5% (primarily 0.2%), with the total claim amount not exceeding 5%-10% of the total contract value. | Large-scale, non-standard projects, industry-standard solutions. |
. The customer deducted 120,000, which is equivalent to deducting the full 10% limit, even if he had no deductible period, he still deducted over 100,000. In essence, they are taking advantage of him by refusing to provide an explanation.
Why do most small and medium-sized enterprises struggle to calculate compensation? The root cause lies in internal management.
90% of disputes are not due to incorrect calculations, but rather a lack of evidence to clearly establish responsibility.
Many mold factories also undertake automation projects, but still rely on outdated management methods: project progress is recorded in the project manager's notebook, changes to the design are communicated verbally, and WeChat chat records are lost when the phone is changed. If a dispute arises, and there is no written or system-generated evidence, the mold factory will be at a disadvantage.
Especially for factories running dozens of projects simultaneously, it's impossible to keep track of which project is at which stage, how long it's been at that stage, and the reason for the delay. Moges has provided project management services to numerous factories, meticulously documenting every step of each automation project and each mold, ensuring that all information is recorded.Each work order can be recorded simply by scanning a code, and nodes awaiting confirmation are directly synchronized to the customer, ensuring a clear record.. If we need to calculate compensation, exporting the records allows us to reconcile with the customer transparently.
In addition to the agreement, include these 3 points to avoid most potential losses:
Most disputes regarding compensation can be avoided upfront by including specific clauses in the contract. I have compiled several essential clauses, which are the result of industry experts' experience:
Clearly define and segment the "delivery" process:Many contracts only specify the total delivery date, without clarifying what constitutes "delivery" (is it when the goods arrive on site, or after commissioning and acceptance?). It is essential to clearly define each stage, including the delivery standards and criteria for delays.
Clearly define the scope of liability and the rules for project delays:Include all reasons and force majeure events specified by the client, and agree that if the delay is caused by the client, the supplier has the right to directly extend the project timeline without incurring any liability.
Must include a compensation cap:Regardless of what the customer says, always include the total claim amount, as per company policy.No more than 10% of the total contract amount..Terms with unlimited clauses should never be signed casually.
Final Note: Earn profits through hard work, don't pay for others' mistakes.
Many small and medium-sized factory owners are constantly focused on how to secure orders, but they often overlook the small details of contract signing and process management. A single failed project can cost three times more than the profits from three successful small projects.
Instead of dealing with legal disputes and endless arguments later, it's better to clearly define the rules and document the process from the beginning. After all, the profits from custom automation are hard-earned, and there's no need to shoulder the blame for someone else's mistakes.