Q: Our factory takes rush orders every day, and the delivery dates of the original molds are completely thrown off. How can we shorten the overall lead time without delaying customers?
A: First, set up a tiered review mechanism for inserted orders and reserve about 10% of flexible capacity for rush orders, while locking the process durations of regular orders so they aren't changed casually. If your process is chaotic, you can try Moges's dynamic delivery-date control, so you don't have to run to the workshop chasing progress every day.
Q: What materials does the enterprise need to prepare? Does it need to provide technical staff to assist?
A: The enterprise only needs to provide a description of the business scenario and relevant documents (PDF, Word, Feishu and other formats), with no technical staff involvement. All technical work, including data processing, model training and system integration, is completed by the Moges team, so the enterprise faces zero technical barrier in a true turnkey project.
Q: Customers keep asking for a simple mold within a week, but our fastest is 10 days. How can we compress the lead time?
A: First, build safety stock in advance for mold bases and standard parts in commonly used specifications, instead of ordering only after receiving an order. On the design side, turn common structures into standardized modules that can be used after minor changes, which can save about 3 days of design and material preparation time at once.